HS2 has moved a 1,600 tonne steel and concrete bridge into place in Saltley, Birmingham in just five hours.
The new Aston Church Road bridge, which is 84 metres long and 21 metres wide, was moved over the existing Birmingham to Derby railway line. It will also sit above the new HS2 tracks as high speed trains travel in and out of Birmingham.
The bridge provides an upgraded, safer section of Aston Church Road including cycleways, which connects Saltley, Washwood Heath and Nechells in north-east Birmingham.
Starting at 10pm on Saturday 10 August, it took five hours for the team to move the bridge into place, reaching its final position at 3am on Sunday morning. The operation was delivered by HS2’s main works contractor in the Midlands, Balfour Beatty VINCI (BBV) and their specialist bridge move contractor Mammoet, during a Network Rail blockade. The railway was handed back to Network Rail five hours earlier than planned.
The technique of building the structure on land next to the existing railway and moving it into position in one operation over one weekend, significantly minimises disruption to rail passengers.
Heavy lifting engineering experts Mammoet moved the bridge into place using two 128-wheeled self-propelled modular transporters (SPMTs) across a matting bed put down over the tracks by Pod-Trak to provide a level surface.
The new bridge was designed by a Design Joint Venture of Mott MacDonald and Systra working for HS2’s main works contractor in the Midlands, Balfour Beatty VINCI (BBV).
The design incorporates local feedback, with a wide pedestrian walkway creating enough space for cyclists, an LED lighting strategy to enhance safety, and new woodland planting around the bridge. Public feedback resulted in the stainless steel finish being replaced with weathered steel panels incorporating a perforated pattern to maximise light and views, making the bridge feel warmer and improving the pedestrian experience.
The composite bridge is made of a concrete deck cast over steel girders with glass reinforced plastic panels used as permanent formwork. One of the UK’s leading concrete frame specialists, MPB delivered the reinforced concrete works.
To prepare for the bridge move, a 9,000m2 platform was made and 62 piles constructed to support concrete structures. Around 4,000m3 concrete and 490 tonnes of reinforced steel has been used in the construction operation.
The bridge now sits on three structures - an abutment to the West of the existing rail tracks, a pier consisting of two columns on the East of the existing tracks, and an abutment to the East of the pier.
In the coming weeks, all the other structures around the bridge, along with the steel assembly of the parapet panels, will be completed.
Over the next 14 months, the original Aston Church Road bridge will be demolished to create the extra space for the HS2 line to pass through, and works will get underway to connect the new bridge to the existing road network.
Construction News
15/08/2024
HS2 Moves 1,600 Steel And Concrete Bridge Into Place In Birmingham


21/05/2025
The University of Warwick's plans to create world-leading STEM facilities have reached a major milestone with the appointment of Kier as the preferred lead contractor for Phase 1 of the STEM Connect Programme.
Located at the university's West Midlands campus, the development will deliver state-of-t

21/05/2025
United Living has announced the acquisition of Peter Duffy Ltd, a Wakefield-based civil engineering contractor with a specialist focus on water infrastructure.
The company will join United Living's Infrastructure Services division and play a key role in the group’s expanding water business.
Found

21/05/2025
Higgins Partnerships and Wandle Housing Association marked a key construction milestone on Monday, 19th May, with a topping out ceremony at the 46–76 Summerstown development in Merton, South London.
Councillors and project partners gathered to celebrate the progress on the eight-storey scheme, whi

21/05/2025
Saint-Gobain has announced plans to open a new low-carbon stone wool insulation manufacturing facility in Melton Mowbray, Leicestershire, as part of its commitment to sustainable construction and net zero carbon emissions by 2050.
Set to begin production in 2027, the plant will initially produce 50

21/05/2025
A former opencast mine near Wigan has been transformed into a vast green space following a major environmental project led by infrastructure company Costain in collaboration with National Highways.
The 34-hectare site, now known as the Sandyforth Green Gateway, has undergone significant ecological

21/05/2025
Farrans Construction has been recognised with a RIBA London Award for Education for its work on the Quadrangle Building project at King's College London, delivered in collaboration with architects Hall McKnight.
The award celebrates the successful transformation of the Department of Engineering’s s

21/05/2025
Dudleys Consulting Engineers has completed the complex remediation of a 12-acre former gas works site near York city centre, paving the way for the development of up to 600 new homes.
The award-winning firm was appointed as the principal engineering partner for ‘The Gas Works’ development, overseei

21/05/2025
Morgan Sindall Construction's Northern Home Counties team has celebrated the topping out of the Oak Wards development at Milton Keynes University Hospital (MKUH), marking a major milestone in the delivery of the vital new healthcare facility.
Dignitaries including Milton Keynes Mayor Councillor Mar

21/05/2025
Regeneration specialist Muse has signed a Pre-Development Agreement (PDA) with Wakefield Council, marking a major step forward in the council's plans to revitalise the city centre.
The agreement follows Wakefield Council's earlier announcement naming Muse as its new Strategic Regeneration Partner.

21/05/2025
Vistry Group has announced the appointment of Dave Bradley as Managing Director of its newly established North Midlands regional business unit.
With an impressive track record in the housebuilding industry, Bradley brings extensive experience from leadership roles at Owl Homes/Partnerships, Piper H