18/08/2023

Network Rail Extends Working Hours At Oxford Station

Network Rail has announced an extension of it working hours on Oxford Station upgrade works to make up for delays caused by historic discoveries at the worksite.

A Victorian brick archway and a hand grenade are among some of the unique challenges that temporarily paused progress on the major project, with round the clock shifts now set to begin.

Work on the £161m Oxford station and railway upgrade had to be paused in June, after contractors unearthed an inverted brick arch under the road at Botley Road bridge.

Ground investigations have since revealed the historic arch is far larger than previously known - reaching a metre deep and stretching around 100 metres - the full length between Mill Street and Frideswide Square.

Archaeologists believe the arch is part of a Victorian water system, designed to keep river water away from the railway and city.

A new work schedule has had to be drawn up to safely remove the brick arch before Network Rail and contractors, Kier Group, can continue to divert the utilities below Botley Road. This will involve the installation of piles to support the bridge and a switch to 24/7 working hours. During this work, a temporary drainage system will be in place to manage groundwater, before a new permanent pumping system is installed later in the project.

From the week commencing Monday 14 August, the team on site will be working from 7am until 7pm, seven days a week. Starting on Saturday 2 September, around the clock work will be carried out on site. To reduce disturbance to those in the area, the nosiest work will be carried out during the day. This revised approach has been agreed with Oxford City Council, in consultation with Oxfordshire County Council. 

-- Advertisement --
hss

The multi-million-pound project to upgrade the station, the railway and the surrounding local road network will boost passengers' travel experience whilst better connecting rail links to the East of Oxford. Once complete, the station and railway upgrades - part of the Oxfordshire Connect programme – will provide travellers with a bigger and better Oxford station and an expanded railway which will enable more services for passengers and freight, with reduced journey times.

The road network near the station will also be improved, with safer junctions with Botley Road and more opportunities for sustainable transport, including enhanced bus travel as well as more space for cyclists and pedestrians through the addition of a four-metre cycle and footway on each side of the main road.

Philip Morton, project manager at Network Rail said: "Whilst we knew the arch was there, it's much larger than our original ground surveys identified, which has added a unique layer of complexity to our ongoing work to upgrade of Oxford station and surrounding areas.

"Due to its potential significance in supporting the bridge, removing the arch from beneath Botley Road is now our biggest challenge, but we're addressing it as safely and efficiently as possible.

"Following further investigations, our new work plan involves installing piles to stabilise the bridge while we excavate the brickwork before we can continue to divert the utilities.

"Going forward, we will be working day and night so we can gain back some of the time lost, with the majority of the noisy work planned to take place during the day, to minimise disruption for the local community. As ever, we appreciate everyone's patience while we manage this unexpected challenge."

Mark Dodd of Oxford Archaeology, said: "The historic city of Oxford contains archaeological remains dating back to the prehistoric period, so there's always the potential to discover a bit of history beneath the ground.

"Owing to the existing road, the site itself wasn't an ideal location for archaeology, so the best approach was for us to be on site whilst the works are underway. It's likely the arch was used to help manage the groundwater owing to its low-lying position close to the river Thames and this is an excellent example of a Victorian engineering solution, as seen elsewhere throughout Britain at this time."

Work was also paused on Thursday 20 July, when a nearby area had to be evacuated following the discovery of a WWII era hand grenade within the work site, near to the railway tracks. Officers from British Transport Police attended the incident, alongside personnel from Explosives Ordinance Disposal.

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
BRICOFLOR UKPro Structures LtdLakeside HireBirmingham Garage & Industrial Doors Ltd123vProboard (G A Imports Ltd)Cleveland Sitesafe LimitedSafety Shield Global Limited123v123v