Armac Demolition has successfully removed a 4,000 tonne two-span bridge over the M42 to make way for the HS2 railway in the West Midlands, on behalf of Balfour Beatty VINCI.
The team used eight 50 tonne excavators and two 40 tonne excavators to remove the 40 metre long, 10 metre wide bridge during a planned 56 hour closure of the motorway. Six articulated dumper trucks transported the excavated material to a local stockpile where it will be crushed and reused on HS2's haul roads and working areas.
The whole job was completed sooner than anticipated, which meant the M42 could be reopened 14 hours ahead of schedule, shortening the closure to 42 hours and reducing disruption to road users.
Armac was working for HS2's civils contractor Balfour Beatty VINCI to deliver the operation during the closure of the M42 near HS2's Interchange Station construction site in Solihull.
HS2 Ltd and Balfour Beatty VINCI worked closely with National Highways and their supply chain to enable the demolition works, with all existing motorway technology diverted or removed prior to the demolition. In the last year, Balfour Beatty VINCI have also diverted power and telecommunications cables away from the structure ahead of the demolition.
The bridge, which carried the A452 over the M42, was removed to allow for a new twin box structure to be constructed, which will carry the high speed line over the motorway in the future. HS2 has built a new, improved road structure and roundabout which now carries the A452, and in future will also enable access to the new HS2 Interchange Station.
Oliver Shore, Construction Director at Balfour Beatty VINCI said: "It is through relentless collaboration with HS2 and National Highways that we have achieved this latest milestone in less than two days, overcoming technical and logistical challenges along the way.
"The demolition of the existing M42 bridge will kickstart the next phase of works, with our attention now turning to the construction of the new twin box structure which is designed to carry Britain's new zero carbon railway – HS2 – over the motorway."
Ian Clarke, Senior Project Manager at HS2 Ltd said: "This is another fantastic milestone for our civils team in the West Midlands, as construction of HS2 moves on at pace. The team did a brilliant job to get the demolition finished way ahead of schedule, meaning the motorway could be reopened much earlier than anticipated."
"In this region, over 9,750 people are working on the many complex and exciting feats of engineering to build HS2 over the existing network of roads, railways, rivers and canals - creating our new zero carbon railway to connect London, the Midlands and the North."
National Highways Senior Network Planner, Frank Bird said: "We'd like to thank motorists for their patience while the work took place and for following our diversion routes during the closure.
"This bridge demolition was a really big project and we have worked closely with HS2 over the past few months to plan the closure of the M42 and to try and limit disruption during the work.
"Given the complexity of the work involved, we're really pleased to see the work completed ahead of time and it's testament to the hard work of those involved that we could open the road earlier than planned."
Noel McLean, Technical Director from Solihull-based Armac Demolition said: ‘'Armac were delighted to be working again in collaboration with our HS2 partners Balfour Beatty VINCI on the first of three major bridge demolition projects in this section. The detailed planning that had been put into the project over the last 12 months by Balfour Beatty VINCI and Armac resulted in an excellent performance over the weekend.
"A safely executed project, completed well ahead of the closure schedule, and not a single mark on the carriageway. Great performance by all involved - looking forward to the next one."
From the full closure of the M42 at 00.25 on Saturday 12 August, a team of 30 people removed the motorway vehicle restraint system and installed protective matting. The 20-strong demolition team then moved in to remove the bridge deck, wing walls, central pier and abutments between 07.30 and 17.00 on Saturday 12 August.
The matting was removed, carriageway cleaned, and central reservation and verge restraint systems reinstated, ready for the motorway to be re-opened at 15.00 on Sunday 13 August.
Coming up next, the Balfour Beatty VINCI team will now start to construct the huge twin box structure, which will carry HS2 trains over the M42. The structure, measuring 300 metres length by 25 metres width will cover around 130 metres of the M42 and will be built in position whilst maintaining three lanes of traffic flowing on the M42.
Construction News
14/08/2023
Armac Remove M42 Bridge To Make Way For HS2


01/05/2025
Willmott Dixon has successfully delivered two state-of-the-art healthcare facilities at the Adanac Health and Innovation Campus in Southampton.
The new facilities include a highly specialised aseptic pharmacy and a Sterile Services Department (SSD), developed in collaboration with Prime plc. The as

01/05/2025
A regeneration scheme has officially begun at the disused Ewenny Road Industrial Estate, as Clowes Developments, in partnership with Bridgend County Borough Council, commences essential enabling works on the site.
The milestone marks the first phase in transforming the brownfield site, which has r

01/05/2025
Neath Port Talbot Council has announced proposals for a new integrated transport hub at the front of Neath railway station, aiming to bring bus, rail, cycling and walking routes together in one central location.
The plans would see the relocation of the current bus station at Victoria Gardens to a

01/05/2025
Work is now underway at Hither Green station as BAM begins a significant upgrade to improve accessibility for thousands of passengers who use the busy London station every day.
Commissioned by Network Rail and the South East Alliance, the £28 million project is funded through the Department for Tra

01/05/2025
Network Rail will be undertaking essential maintenance work on the Heart of Wales line between Llanwrtyd and Pantyffynnon from Tuesday 6 May to Friday 23 May,
The closure will allow engineering teams to carry out a series of vital upgrades and repairs in one coordinated effort, helping to minimise

01/05/2025
Jessica Morden MP, Chair of the Parliamentary Labour Party and Member of Parliament for Newport East, recently visited Persimmon Homes East Wales' Springfield Meadows development, part of the £1 billion Glan Llyn regeneration project.
The current phase of the scheme will deliver 178 new homes, with

01/05/2025
Park Gate, a flagship development by Vistry at Lea Castle, has received full Building with Nature accreditation, recognising its strong commitment to ecological sustainability and wildlife protection at the heart of the 600-home project.
The accreditation reflects Vistry's efforts to embed green in

01/05/2025
Unite Students has entered into a joint venture (JV) agreement with Manchester Metropolitan University to deliver 2,300 new student beds in the heart of Manchester, in a development valued at approximately £390 million.
The strategic partnership will see Unite hold a 70% stake in the JV and act as

01/05/2025
Plans to reconnect Golborne to the national rail network for the first time in over six decades have taken a major step forward, after Wigan Council approved the planning application for the town’s new railway station.
Transport for Greater Manchester (TfGM) has also confirmed the appointment of Go

01/05/2025
Roof lanterns are one of the star players in the world of skylights, bringing a touch of glamour and luxury to a growing number of homes across the UK.
If you have one at the top of your wish list, we’re here to help with expert advice, top brand rooflights and a roof lantern buyer's guide to ligh