The cost to refurbish the Big Ben tower clock in London has more than doubled in price to over £60 million, it has been revealed.
With Sir Robert McAlpine being confirmed as the contractor for the project, the scheme's cost has rocketed from its original £29m valuation to £61m.
The new costs figure follows 16 months of detailed analysis of the work required to refurbish the Elizabeth Tower and Great Clock.
Reasons for the increased costs include an increased understanding of what work is needed. A lot more information is now known about the condition of the stonework following a further stone survey undertaken after the initial estimate. With the design having gone through a Detailed Design and Technical Design process, the company now understands the extend of the refurbishment work required throughout the Elizabeth Tower.
In addition, it was found that the processes for completing the works was more complex, and therefore more expensive, than previously thought. Examples include re-glazing the clock faces, stripping and repainting metal work within the tower, and the associated sequencing which the works can be completed to ensure a high quality of workmanship: the gilding cannot be completed until all the stripping and repainting of the metal work has been completed.
Ground conditions at the site have also proved to be more complex than anticipated and will require additional work. As an example, the quantity of utility services discovered in the ground in Speaker’s Green and New Palace Yard, was greater than what had previously been identified through the surveys and historic record information. This meant that further ground works were required to support the weight of the scaffolding.
Overall, the total cost of the project, including VAT, Risk and Optimism Bias and the transferred fire safety work costs, is therefore now estimated at £61m as opposed to £29m as estimated in spring 2016.
In a statement, the Clerk of the House of Commons, the Clerk of the Parliaments and the Director General said they acknowledge there have been estimating failures.
"In advance of tendering contracts, the initial high level estimates were set at a lower level to avoid cost escalation from the market," the statement said.
"Subsequent estimates, using better data and more extensive surveys, better reflect the true likelihood of the costs. We believe that we now have a more accurate estimate of the cost of the works and will report regularly to the committees on the progress of work."
The authorities of both Houses had already agreed to an internal audit review of progress on the Elizabeth Tower project, and this will now include analysis of the reasons for the increase in estimated costs.
(LM)
Construction News
02/10/2017
Big Ben Refurb Cost Jumps To £61m


21/05/2025
The University of Warwick's plans to create world-leading STEM facilities have reached a major milestone with the appointment of Kier as the preferred lead contractor for Phase 1 of the STEM Connect Programme.
Located at the university's West Midlands campus, the development will deliver state-of-t

21/05/2025
United Living has announced the acquisition of Peter Duffy Ltd, a Wakefield-based civil engineering contractor with a specialist focus on water infrastructure.
The company will join United Living's Infrastructure Services division and play a key role in the group’s expanding water business.
Found

21/05/2025
Higgins Partnerships and Wandle Housing Association marked a key construction milestone on Monday, 19th May, with a topping out ceremony at the 46–76 Summerstown development in Merton, South London.
Councillors and project partners gathered to celebrate the progress on the eight-storey scheme, whi

21/05/2025
Saint-Gobain has announced plans to open a new low-carbon stone wool insulation manufacturing facility in Melton Mowbray, Leicestershire, as part of its commitment to sustainable construction and net zero carbon emissions by 2050.
Set to begin production in 2027, the plant will initially produce 50

21/05/2025
A former opencast mine near Wigan has been transformed into a vast green space following a major environmental project led by infrastructure company Costain in collaboration with National Highways.
The 34-hectare site, now known as the Sandyforth Green Gateway, has undergone significant ecological

21/05/2025
Farrans Construction has been recognised with a RIBA London Award for Education for its work on the Quadrangle Building project at King's College London, delivered in collaboration with architects Hall McKnight.
The award celebrates the successful transformation of the Department of Engineering’s s

21/05/2025
Dudleys Consulting Engineers has completed the complex remediation of a 12-acre former gas works site near York city centre, paving the way for the development of up to 600 new homes.
The award-winning firm was appointed as the principal engineering partner for ‘The Gas Works’ development, overseei

21/05/2025
Morgan Sindall Construction's Northern Home Counties team has celebrated the topping out of the Oak Wards development at Milton Keynes University Hospital (MKUH), marking a major milestone in the delivery of the vital new healthcare facility.
Dignitaries including Milton Keynes Mayor Councillor Mar

21/05/2025
Regeneration specialist Muse has signed a Pre-Development Agreement (PDA) with Wakefield Council, marking a major step forward in the council's plans to revitalise the city centre.
The agreement follows Wakefield Council's earlier announcement naming Muse as its new Strategic Regeneration Partner.

21/05/2025
Vistry Group has announced the appointment of Dave Bradley as Managing Director of its newly established North Midlands regional business unit.
With an impressive track record in the housebuilding industry, Bradley brings extensive experience from leadership roles at Owl Homes/Partnerships, Piper H