Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 146,423 companies....

Construction News

02/10/2017

Big Ben Refurb Cost Jumps To £61m

The cost to refurbish the Big Ben tower clock in London has more than doubled in price to over £60 million, it has been revealed.

With Sir Robert McAlpine being confirmed as the contractor for the project, the scheme's cost has rocketed from its original £29m valuation to £61m.

The new costs figure follows 16 months of detailed analysis of the work required to refurbish the Elizabeth Tower and Great Clock.

Reasons for the increased costs include an increased understanding of what work is needed. A lot more information is now known about the condition of the stonework following a further stone survey undertaken after the initial estimate. With the design having gone through a Detailed Design and Technical Design process, the company now understands the extend of the refurbishment work required throughout the Elizabeth Tower.

In addition, it was found that the processes for completing the works was more complex, and therefore more expensive, than previously thought. Examples include re-glazing the clock faces, stripping and repainting metal work within the tower, and the associated sequencing which the works can be completed to ensure a high quality of workmanship: the gilding cannot be completed until all the stripping and repainting of the metal work has been completed.

-- Advertisement --
hss

Ground conditions at the site have also proved to be more complex than anticipated and will require additional work. As an example, the quantity of utility services discovered in the ground in Speaker’s Green and New Palace Yard, was greater than what had previously been identified through the surveys and historic record information. This meant that further ground works were required to support the weight of the scaffolding.

Overall, the total cost of the project, including VAT, Risk and Optimism Bias and the transferred fire safety work costs, is therefore now estimated at £61m as opposed to £29m as estimated in spring 2016.

In a statement, the Clerk of the House of Commons, the Clerk of the Parliaments and the Director General said they acknowledge there have been estimating failures.

"In advance of tendering contracts, the initial high level estimates were set at a lower level to avoid cost escalation from the market," the statement said.

"Subsequent estimates, using better data and more extensive surveys, better reflect the true likelihood of the costs. We believe that we now have a more accurate estimate of the cost of the works and will report regularly to the committees on the progress of work."

The authorities of both Houses had already agreed to an internal audit review of progress on the Elizabeth Tower project, and this will now include analysis of the reasons for the increase in estimated costs.

(LM)

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Pro Structures LtdBRICOFLOR UKLakeside HireExecutive LeisureStainless & Aluminium ServicesProcter Fencing SuppliesVectaire LtdAir Vent TechnologyMaster Build Team (MBT Group)CT Surveys Ltd