08/03/2012

First Enabling Works On Hammersmith Flyover Completed

The first key enabling works to allow the Hammersmith Flyover to be fully reopened to traffic have now been completed, Transport for London (TfL) have announced.

The works, which began in January, have seen around 200m of the central reservation along the flyover removed in preparation for new tensioning cables to be installed which will support the structure.

Using a number of specialist techniques including hydrodemolition and diamond cutting, around 140 tonnes of concrete have been removed by using both high pressurised water and a rotating cord impregnated with diamonds to cut the material away.

These techniques meant that work could be carried out safely while traffic continued to use the flyover.

A team of engineers are working 24 hours a day, seven days a week to complete the work, often in a crawl space far less than human height.
-- Advertisement --
hss



Now the key enabling works have been completed, TfL will begin to install a new concrete base, drainage and tailored anchorages for the new cables within the structure.

The design for the new post-tensioning system will see new cables installed above and below the bridge deck inside a specially made duct, which will supplement the load capacity of the remaining cables.

The new ducts will then be filled with a wax oil to prevent deterioration from any water ingress, as well as enable the cables to be easily replaced as and when required.

Work to strengthen the five weakest spans of the 16 span structure will be completed ahead of the 2012 Games, ensuring that the flyover can carry full traffic loading during the Games and for many decades to come.

Following the Games, TfL will return to the structure to strengthen the remaining spans. This work however will not require further weight restrictions to be imposed and TfL hope to complete it with only off peak lane closures, causing much less disruption than is presently the case.

Garrett Emmerson, Chief Operating Officer for Surface Transport at TfL, said: "We are continuing to work round the clock to implement a long term solution to restore the Hammersmith Flyover to full traffic capacity.

"With key enabling works now completed, work is now fully underway to install the new cabling system which will allow the structure to remain in use for many decades to come."

(CD/GK)

Latest Construction News

07/05/2025
Willmott Dixon has been selected by Great Yarmouth Borough Council as its development partner for the regeneration of the town's North Quay waterfront. The £20 million transformation of the 10.5-acre site will see the creation of a vibrant mixed-use destination, incorporating leisure and retail fac
07/05/2025
Costain has been selected to support the Department for Transport (DfT) by providing specialist technical and commercial advice to develop a range of rail infrastructure enhancement projects in the Western, Wales and Wessex regions. Costain will lead a consortium of specialists including GHD, InteG
07/05/2025
Adler & Allan, the Goldman Sachs-backed environmental services leader, has acquired Glanville Environmental, a specialist in drainage and civil engineering, in a move aimed at expanding its ability to address environmental issues such as pollution reduction and water resource management across the S
07/05/2025
Lovell has received full planning approval from Somerset Council to build 80 new homes in the village of Cotford St Luke, near Taunton, following unanimous approval of the site's reserved matters application. The £25 million development will be located off Dene Road, approximately five miles from T
07/05/2025
SSD Safety Services is reinforcing its commitment to workplace safety by offering professional PPE equipment servicing for businesses across Surrey and surrounding areas. With growing demands and the increasing importance of health and safety in high-risk industries, the company delivers critical
07/05/2025
Procurement organisation Fusion21 has unveiled the 40 specialist firms appointed to its £1.5 billion Decarbonisation Framework. The framework, which runs on a turnkey delivery model, is designed to accelerate domestic and non-domestic retrofit programmes across the UK. Of the appointed suppliers, 4
07/05/2025
Windsor-based developer Castlemere Developments has partnered with estate agency Circa London to launch its £9.6 million townhouse development in Dulwich to buyers in the Far East. The six-property scheme, known as Melbourne Mews, marks Castlemere's first venture into international marketing and is
07/05/2025
Harlington Station is set to receive a major infrastructure overhaul as Network Rail begins work on a new footbridge, replacing the station's decades-old structure in a £7.9 million upgrade aimed at improving passenger safety, accessibility and long-term reliability. The new footbridge, designed to
07/05/2025
The long-term regeneration of Birmingham’s Ladywood Estate has taken a major step forward as St Joseph, part of the Berkeley Group, officially signed a Development Agreement with Birmingham City Council to transform the estate over the next two decades. The agreement confirms that at least 70% of e
07/05/2025
As businesses across the South West adapt to new hybrid working models, Gloucester's £107 million Forum development is becoming the region’s go-to destination for modern, flexible workspaces. Led by Gloucester City Council in partnership with Reef + Partners, Forum is redefining what office life ca
Lakeside HireAqua Direct LtdStuart CanvasT & D Glazing And Installation LimitedEfco UK LtdMAX PUMP concrete pumping and liquid screedLoft Boarding MidlandsAndy Thornton LtdLS Engineering (Shropshire) LimitedCGL Roofing