Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 157,474 companies....

Construction News

26/02/2009

New State-Of-The-Art Facilities For Lincoln Minster School Relies On A Contiguous Piled Wall Solution

Construction News Image
Project Overview

The concept for the new facilities was based on excavating the site to provide the extra room required for the development.
This required a contiguous pile retaining wall to support the surrounding ground and neighbouring roads. Van Elle, one of the UK's leading piling and ground engineering specialists were contracted to carry out all the piling works on this technically challenging site, as their expertise had been proven on similar projects.

The piling works, awarded by main contractor Quibell, worth over £400k involved a total of 298 No. Duplex and CFA piles.

In addition to the piling works, Van Elle's geotechnical team carried out a series of boreholes - as only limited information was available during the early tender stages. This gave a better picture of the actual ground conditions enabling Van Elle's engineers to make an informed choice of piling method.

The issues and the solutions

Not only is the school on a steep hillside surrounded by historic buildings, there is also a convent within 4m of the piling site and an adjacent main road. Lincoln itself sits on a rocky outcrop of Lincolnshire limestone with made ground above, making the ground conditions as challenging to work with as the site itself.
-- Advertisement --
hss



Because of these issues the use of Duplex piles was the only economical and practical solution. The Duplex piling method allowed the piles to be temporary cased through the made ground and socketed a minimum of 5m below dredge level into the bedrock.

The site was live during term time and as well as restricted access to and on site, deliveries could not be accepted before 9.30am and after 3.30pm to ensure the safety of the students and parents. This meant rig choice and logistics were crucial. Rigs were selected based on their size, weight and manoeuvrability as well as their suitability for the job. Well planned logistics and pre-ordered deliveries meant that there were no delays waiting for materials to arrive.

Construction

188 No. Duplex piles were drilled to form the contiguous wall, 660mm diameter temporary casing was drilled 5m onto the rock then the rock was drilled out using rotary percussive and Down The Hole Hammer techniques. The bore was then tremied with concrete, reinforcement was installed and the temporary casing removed.

The site investigation showed potential shallow mine workings at 1-2m deep along the south and east sides of the site. Van Elle solved this problem by pumping in a weak concrete grout, allowing it to set then re-boring through the concrete to form the Duplex piles.

The contract was complete within the anticipated programme and budget, even with the several unexpected challenges which arose during construction.

The retaining wall has now been excavated out by main contractor Quibell, and the steel frame is also being erected. The project is due for completion in 2010 when the students will be able to enjoy their new facilities.

Latest Construction News

09/07/2025
Network Space Developments has formally submitted an outline planning application to redevelop the former Cadent Gas Works site on Winwick Road, just north of Warrington town centre. The plans propose up to 100,000 sq ft of high-quality employment space, intended to accommodate a range of industria
09/07/2025
The City of London Corporation has granted planning permission for two major high-rise schemes at opposite ends of the City's historic skyscraper cluster, reinforcing the Square Mile’s reputation as a global business and cultural hub. The approved projects, a 45-storey tower at 63 St Mary's Axe and
09/07/2025
Construction firm Kier has signed a Pre-Construction Services Agreement (PCSA) with global healthcare company Haleon to deliver a state-of-the-art Oral Health Innovation Hub in Weybridge, Surrey. The landmark project, announced by the UK Government during its International Investment Summit, will p
09/07/2025
One of the UK's largest housebuilders, Persimmon Homes Severn Valley, has submitted detailed proposals for the construction of 562 new homes in Cribbs Causeway, as part of the next phase of its major Fishpool Hill development near Bristol. The latest reserved matters applications cover phase two of
09/07/2025
The Transpennine Route Upgrade (TRU) has reached a significant milestone, following five consecutive weekends of intensive engineering work between Leeds and York to advance electrification of the line. As part of the ongoing upgrades, engineers have now installed 7.5 kilometres of overhead line eq
09/07/2025
Plans to transform the Teviot Estate in Poplar have reached a major milestone, with Tower Hamlets Council granting a resolution to approve the £800 million redevelopment at its Strategic Development Committee meeting on Tuesday, 8 July. The Hill Group and housing association Poplar HARCA are leadin
09/07/2025
Wates has joined Stepnell, Morgan Sindall, Kier, and BAM as a Gold Corporate Partner of the Centre for Construction Best Practice (CCBP), marking a major milestone in efforts to improve collaboration, innovation, and delivery standards across the UK construction sector. The five major contractors a
09/07/2025
Roger Bullivant Limited (RBL) has been appointed by main contractor McLaren to carry out piling works for a new Boxing Academy and school development in Hackney, East London. The high-profile project, commissioned by the Department for Education and the Boxing Academy Trust, will transform an unfin
09/07/2025
Key redevelopment projects at Central Library and Peterscourt, part of the wider Vine Towns Fund initiative, are set to move forward as Cabinet prepares to review an update and approve contracts at a meeting on 15 July. The update outlines the final phase of the £25 million Vine project, which is p
09/07/2025
Seven of the UK's largest housebuilders have offered a combined £100 million settlement in response to a Competition and Markets Authority (CMA) investigation into alleged information sharing practices that raised competition concerns. The CMA launched the probe last year amid suspicions that Barra
Stuart CanvasLakeside HireAqua Direct LtdEfco UK LtdMudfords LtdTraining Courses 4 U LtdNationwide Louvre CompanyMetal Sheets LtdSteel ExpressVinco Sales