Project Overview
The concept for the new facilities was based on excavating the site to provide the extra room required for the development. This required a contiguous pile retaining wall to support the surrounding ground and neighbouring roads. Van Elle, one of the UK's leading piling and ground engineering specialists were contracted to carry out all the piling works on this technically challenging site, as their expertise had been proven on similar projects.
The piling works, awarded by main contractor Quibell, worth over £400k involved a total of 298 No. Duplex and CFA piles.
In addition to the piling works, Van Elle's geotechnical team carried out a series of boreholes - as only limited information was available during the early tender stages. This gave a better picture of the actual ground conditions enabling Van Elle's engineers to make an informed choice of piling method.
The issues and the solutions
Not only is the school on a steep hillside surrounded by historic buildings, there is also a convent within 4m of the piling site and an adjacent main road. Lincoln itself sits on a rocky outcrop of Lincolnshire limestone with made ground above, making the ground conditions as challenging to work with as the site itself.
Because of these issues the use of Duplex piles was the only economical and practical solution. The Duplex piling method allowed the piles to be temporary cased through the made ground and socketed a minimum of 5m below dredge level into the bedrock.
The site was live during term time and as well as restricted access to and on site, deliveries could not be accepted before 9.30am and after 3.30pm to ensure the safety of the students and parents. This meant rig choice and logistics were crucial. Rigs were selected based on their size, weight and manoeuvrability as well as their suitability for the job. Well planned logistics and pre-ordered deliveries meant that there were no delays waiting for materials to arrive.
Construction
188 No. Duplex piles were drilled to form the contiguous wall, 660mm diameter temporary casing was drilled 5m onto the rock then the rock was drilled out using rotary percussive and Down The Hole Hammer techniques. The bore was then tremied with concrete, reinforcement was installed and the temporary casing removed.
The site investigation showed potential shallow mine workings at 1-2m deep along the south and east sides of the site. Van Elle solved this problem by pumping in a weak concrete grout, allowing it to set then re-boring through the concrete to form the Duplex piles.
The contract was complete within the anticipated programme and budget, even with the several unexpected challenges which arose during construction.
The retaining wall has now been excavated out by main contractor Quibell, and the steel frame is also being erected. The project is due for completion in 2010 when the students will be able to enjoy their new facilities.
Construction News
26/02/2009
New State-Of-The-Art Facilities For Lincoln Minster School Relies On A Contiguous Piled Wall Solution


21/05/2025
The University of Warwick's plans to create world-leading STEM facilities have reached a major milestone with the appointment of Kier as the preferred lead contractor for Phase 1 of the STEM Connect Programme.
Located at the university's West Midlands campus, the development will deliver state-of-t

21/05/2025
United Living has announced the acquisition of Peter Duffy Ltd, a Wakefield-based civil engineering contractor with a specialist focus on water infrastructure.
The company will join United Living's Infrastructure Services division and play a key role in the group’s expanding water business.
Found

21/05/2025
Higgins Partnerships and Wandle Housing Association marked a key construction milestone on Monday, 19th May, with a topping out ceremony at the 46–76 Summerstown development in Merton, South London.
Councillors and project partners gathered to celebrate the progress on the eight-storey scheme, whi

21/05/2025
Saint-Gobain has announced plans to open a new low-carbon stone wool insulation manufacturing facility in Melton Mowbray, Leicestershire, as part of its commitment to sustainable construction and net zero carbon emissions by 2050.
Set to begin production in 2027, the plant will initially produce 50

21/05/2025
A former opencast mine near Wigan has been transformed into a vast green space following a major environmental project led by infrastructure company Costain in collaboration with National Highways.
The 34-hectare site, now known as the Sandyforth Green Gateway, has undergone significant ecological

21/05/2025
Farrans Construction has been recognised with a RIBA London Award for Education for its work on the Quadrangle Building project at King's College London, delivered in collaboration with architects Hall McKnight.
The award celebrates the successful transformation of the Department of Engineering’s s

21/05/2025
Dudleys Consulting Engineers has completed the complex remediation of a 12-acre former gas works site near York city centre, paving the way for the development of up to 600 new homes.
The award-winning firm was appointed as the principal engineering partner for ‘The Gas Works’ development, overseei

21/05/2025
Morgan Sindall Construction's Northern Home Counties team has celebrated the topping out of the Oak Wards development at Milton Keynes University Hospital (MKUH), marking a major milestone in the delivery of the vital new healthcare facility.
Dignitaries including Milton Keynes Mayor Councillor Mar

21/05/2025
Regeneration specialist Muse has signed a Pre-Development Agreement (PDA) with Wakefield Council, marking a major step forward in the council's plans to revitalise the city centre.
The agreement follows Wakefield Council's earlier announcement naming Muse as its new Strategic Regeneration Partner.

21/05/2025
Vistry Group has announced the appointment of Dave Bradley as Managing Director of its newly established North Midlands regional business unit.
With an impressive track record in the housebuilding industry, Bradley brings extensive experience from leadership roles at Owl Homes/Partnerships, Piper H