CASE STUDY: Furukawa EFLEX Square Cable Ducting Solves Space and Cost Challenges for a High-Density Data Centre

In 2024, E-Tech Components successfully assisted a 90MW Tier 3 data centre (LON01) in North London. Our team supported major drainage and underground ductwork for a new substation within the wider data centre infrastructure, serving Building 1, a 20MW, four–data-hall facility within a high-density, two-building campus. Below is some top-level information about the site and its new data centre cable ducting system:

Location: Brent Cross, London Borough of Barnet, UK

Programme: January 2024 – May 2024 (19 weeks)

Site Size: 8.92 acres | 86,527 sq. m

Wider Impact: £1 billion of investment into the local economy during construction

Client’s Pain Points

The client required a cable ducting system that could perform in a constrained, fast-moving data centre environment while supporting future scalability. Key concerns included:

• Limited space across a high-density campus

• Tight construction timelines with no tolerance for delays

• The need to accommodate design changes without rework

• Minimising excavation, trench size and installation disruption

• Long-term durability and protection for critical power and data cabling

The Challenge

For a Tier 3 data centre, cable infrastructure must meet the highest standards for resilience, safety and future-readiness. The ducting solution for Building 1 had to be:

• Compact and space-efficient

• Quick to install to maintain programme certainty

• Flexible enough to adapt to evolving layouts

• Robust enough to support underground ductwork (multi-rack cable routes)

• Fully compliant with relevant industry standards

Any delays or design constraints would risk impacting the wider campus delivery schedule.

Why They Chose E-Tech

E-Tech Components was selected for its technical expertise, reliability and collaborative approach. By working closely with all project stakeholders, E-Tech ensured:

• Clear technical guidance from design through to delivery

• Guaranteed product availability and on-time supply

• Full accessory support to avoid installation bottlenecks

• Practical solutions tailored to real site constraints

-- Advertisement --
hss

Our proven experience in data centre infrastructure gave the client confidence that the cable ducting system would be delivered safely, efficiently and without compromise.

Our Solution: EFLEX Square – Data Centre Cable Ducting by Furukawa Electric

EFLEX Square is a modular, stackable ducting solution ideal for underground multi-rack cable routes in data centre infrastructure.

Built to ENATS 12/24 Class 1, EFLEX Square enables faster, cleaner installs while maximising space and protection. Besides data centres, this proven solution is trusted across Europe and the Middle East for use in highways, rail networks, stadiums and airports.

By supplying Furukawa EFLEX Square, the system’s flexibility allowed our client to create custom layouts without bends or spacers, speeding up installation and minimising trench size.

Why Choose Furukawa EFLEX Square?

Water-Tight to IP67

• Dust-Proof

• Strong and Durable

• Easily Installed

• Stackable

• Lightweight and Versatile

• Cost-Saving

• Flame-Resistant

• Space-Saving

Flexible Underground Ductwork (Cable Ducting) for Data Centres

Underground ductwork (cable ducting) safely routes power and data. This is crucial for complexes where uptime, organisation and protection matter most. Ducting shields cables from weather, leaks, contamination, impact and interference, keeping networks protected, organised and future-ready.

Furukawa EFLEX Square – A Smarter Way to Bury Cable

EFLEX Square comes in 5 sizes with a full range of accessories. It allows data centres to design multi-rack duct layouts without costly bend pieces or spacers. It seamlessly integrates with Green Trough to deliver a complete, top-tier cable management solution.

• Stackable units only need small trenches with no spacers – ideal for tight sites

• Just 6.4kg for a 5.3m (100 series) unit – easy to handle on-site

• Withstands 25-tonne loads buried at just 300mm – shallower trenches, lower costs

• Bends up to 10× its inner diameter – no expensive bend pieces needed

• Chemical-resistant for long-term reliability underground

• Easy to configure with 5 size options and IP67-rated watertight push-fit connectors

Installation Method

Installing flexible underground ducting is straightforward but requires careful planning to ensure safety and compliance.

Testing

Threat – Water Ingress

Protection Level – IP67-rated connectors; moisture-activated Aqua seals

Threat – Rodents

Protection Level – HDPE material offers a strong physical barrier

Threat – Dust / Dirt Ingress

Protection Level – Sealed design protects interior from dust and soil intrusion

EFLEX Square Accessories & Complete Cable Ducting System

To complete your Furukawa EFLEX system installation, E-Tech Components supplies a full range of compatible accessories designed for seamless connection, protection and flexibility.

• Furukawa EFLEX Square Duct – Sizes 50, 75, 100, 130 and 150 — robust, flexible underground ductwork (ducting) for fast cable installation.

• Furukawa AQUA Square Adaptor – Jointing mechanism used to connect cut EFLEX Square Duct ends when adjusting length.

• Furukawa AQUA Square Male Adaptor – Converts a pipe section to male for insertion into a female part.

• Furukawa AQUA Connector – Includes AQUA-Nut and AQUA-Mouth to connect EFLEX Square / Round ducts to chambers or catchpits.

• Furukawa Male to Male Adaptor – Converts female ends to male, linking two EFLEX female connectors or a female end to a Long Bell Mouth.

• Furukawa Converter to EFLEX Round – Adaptor connecting EFLEX Square male ends to other pipe types.

• Furukawa Long Bell Mouth – Connects EFLEX Square to chambers / catchpits — available in three lengths for wall thickness.

• Furukawa Bell Block – Concrete resin block for interfacing EFLEX with concrete or polymer chambers.

• Furukawa Temporary Plug – Used with the EFLEX Square Long Bell Mouth and standard EFLEX Square units to prevent dirt, sand or soil from entering the duct during installation.

etechcomponents.com/

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Lakeside HirePro Structures LtdBRICOFLOR UKAiros DevelopmentsAdam Fahey DesignLPH ConstructionGLW Engineering & Construction LtdThe Root Barrier StoreAbacus Garage Door Solutions LtdConcrete Canvas Ltd