Esh Construction Completes Upgrade Of Ash Barge Dock

The Ash Barge Dock at Northumberland Energy Park (NEP) has undergone a major transformation following the completion of complex infrastructure works by Esh Construction in partnership with Advance Northumberland.

Located near the Port of Blyth, NEP is a key part of Energy Central—the UK’s strategic offshore energy and subsea services hub. The redevelopment of the Ash Barge Dock is a critical component of Phase 1 enabling works, aimed at enhancing the site’s capabilities for industrial operations, particularly in the renewable energy and offshore markets.

The extensive upgrade began in June 2024 and saw the installation of 173 tubular steel piles, each with a diameter of 610mm and driven to depths of 16m to 18.5m. These piles support a newly constructed 1-metre-deep reinforced concrete relieving slab, adjacent to the dock’s West and North quay walls.

-- Advertisement --
hss

In total, 3,000m³ of concrete was used to form the relieving slab, which provides a safe working load of 5,300kN, enabling the dock to handle heavy industrial loads including the import and export of large components and finished goods.

Esh Construction also cast transition slabs, measuring 540mm thick with a concrete volume of 700m³, behind the relieving slab. A further 8,100m² of reinforced concrete paving was laid at 300mm depth, creating a durable surface to support vehicle movement and operations.

The entire concreting phase was delivered through 60 separate pours, with the total volume exceeding 6,130m³.

Additional site work included the decommissioning of two 4m diameter culverts, remnants from the former Blyth power station. Hydro-demolition techniques were used to safely remove eight 30-tonne mooring bollards, which have now been replaced with upgraded 50-tonne and 100-tonne bollards and foundations, improving mooring capabilities for larger vessels.

The dock's drainage system was also modernised with over 440m of QMAX drainage channels, connected to a new stormwater management system, which includes bypass interceptor tanks and outfalls to efficiently handle surface water runoff.

The completed works now position Ash Barge Dock as a fully operational, heavy-duty berth equipped to serve the growing needs of the offshore and renewable energy industries in the North East.

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Lakeside HirePro Structures LtdBRICOFLOR UKgrade 1 hire - Pipie Clampsgrade 1 hire - Props, Strongboys, Underpinning Jacks And Formwork.Grade 1 Hire - Rubbish ChutesPace ConsultAxis Entrance Systems LtdKirby and Wells Ltd -  Kawstore  (CompanyID 491878 / CopyId 228904)Ceildoor Products Limited