An £830,000 scheme to improve the roads around Ripon Market Place has been completed seven weeks ahead of schedule, with the roads now reopened for use.
The first phase of works was carried out in November, followed by the second phase, which started in January to avoid disruption during the busy festive season.
Cllr Keane Duncan, Executive Member for Highways and Transport, said: "This has been one of the most extensive and complex set of resurfacing works we’ve conducted in recent months.
"So, we are delighted that the work in Ripon Market Place has been completed many weeks ahead of schedule.
"This has been possible because it was delivered by our council-owned company, NYHighways. This has ensured excellent value for money, allowed extended working hours and meant it was possible to respond quicker to local feedback.
"I would like to thank the public for their patience and understanding during the works."
The work involved replacing the old, problematic block paving with a more durable asphalt surface that will ensure the area is fit for the future. The new surface is designed to avoid the unsightly defects that had caused regular disruptions and repairs. Key areas of block paving have been retained to preserve the heritage and character of the historic market place.
Cllr Andrew Williams, who represents the Ripon Minster and Moorside division on North Yorkshire Council, added: "I am delighted that we have been able to complete this scheme seven weeks ahead of schedule.
"I am grateful for the efforts of our highways team who have led on this project and have delivered a scheme which has given Ripon smooth and level roads which are a pleasure to drive upon.
"I know that these works have caused an inconvenience for our business community, but I believe that everyone will now be able to reap the benefits of having safe roads in the market place."