Construction News

18/10/2024

Leviat Ensures HS2 Tunnel Construction Remains On Track

Faced with materials shortages at the HS2 Copthall tunnel construction, the Skanska Costain STRABAG joint venture (SCS JV) turned to Leviat for training, specialist equipment and ongoing support in order to create an on-site steel threading facility capable of producing the required 92,000 rebar couplers.

This innovative and efficient rebar facility removes the risk of delays, enables new jobs, reduces lorry movements, cuts waste and saves at least £22m.

A shortfall in the marketplace of available prefabricated fatigue-rated rebar couplers meant the construction of the HS2 tunnel in Hillingdon would face unnecessary project delays. SCS JV required a solution that would supply fatigue rated, and CARES certified mechanical reinforcement connections that met the requirements of the HS2 construction programme. With comprehensive and ongoing support from Leviat, this led to the creation of an on-site rebar threading facility for a project on this scale.

Following meetings with the SCS JV Senior Project Manager, Leviat recommended the optimum approach would be to manufacture the couplings on-site by placing Bartec/CXL threading equipment close to the tunnel operations. Leviat provided extensive ongoing advice and support on the site layout, procurement of roller tables, energy and ancillary equipment, and staff training.

-- Advertisement --
hss

A critical element was expediting the CARES TA1-A&B certification (Certification Authority for Reinforcing Steels) for the threading site. Leviat’s information and guidance combined with technical know-how and frequent site visits ensured this certification was secured in a timely fashion.

With the factory production control regime established and approved, the production team could purchase stock rebar and then complete the processing operations on site, before taking it through the four-step threading process and delivering it to the Copthall tunnel construction area.

Ray Moloney, Senior Project Manager for SCS JV said: "In mid-2022 we started engaging with partners including Leviat and CARES to develop an on-site processing scheme and within 20 weeks, we were processing our first order."

"The solution has created new jobs, offered new training opportunities for engineers and means that we can remove the risk of any delays in construction due to supply shortages," added Ray Moloney.

Rob Helliwell, Business Development Manager, Structural Connections UK at Leviat said: "Transforming what was essentially a field into the onsite facility we see today has been an incredible undertaking but we are immensely proud to have played our part in the delivery of such an innovative and sustainable onsite solution. The professionalism and collaborative approach by Raymond Moloney BSc(Hons), MIEI and his team at Skanska Costain STRABAG Joint Venture with Leviat in the UK and Ireland has been exemplary throughout the process.

"We look forward to continuing to support the Copthall Tunnel and the other opportunities this undoubtedly creates for other HS2 (High Speed 2) Ltd projects and the wider construction industry."

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
BRICOFLOR UKLakeside HirePro Structures LtdAsbestos-sampling.comNew Home Quality ControlCabinlocator LtdOriginal Style by Hyperion TilesBuild WarrantyFire and Acoustic Seals LtdFerrari Fan Technology (UK) Limited