Work Complete On Bromford Tunnel Portal At Washwood Heath

Construction News Image
Work to develop the 3.5 mile Bromford Tunnel bringing high speed trains into Birmingham has taken a leap forward as excavation of the 22 metre deep west portal is completed.

The portal at Washwood Heath has been finished in readiness for the two 1,600 tonne tunnel boring machines (TBMs) building the twin-bore tunnel to complete their journeys from Water Orton in North Warwickshire.

The huge earthworks operation has taken a team of 130 people from HS2’s construction partner Balfour Beatty VINCI (BBV) nine months to complete.

Groundwork specialists from Coventry-based Duo Group supported BBV with the complex excavation programme to extract 53,400m3 of earth from the ground. The spoil has been transported on specially built haul roads to support construction of the Delta Junction – a triangular section of 13 viaducts in North Warwickshire.

-- Advertisement --
hss

The Washwood Heath portal is the deepest of four tunnel portals on the Midlands section of the HS2 route. A two-year programme of ground reinforcement works, delivered by the Bachy Soletanche and Balfour Beatty Ground Engineering joint venture (known as SB3), began in November 2021 to prepare for the portal’s excavation.

The portal is at the start of a 750-metre-long cut and cover structure, which is currently being excavated and built by SB3. This is where HS2 trains will emerge from the tunnel and travel below ground level, before raising up onto a series of viaducts into Birmingham’s Curzon Street Station.

'Mary Ann', the first TBM to launch from Water Orton in 2023, is expected to break through the portal wall at Washwood Heath by the end of 2024, with the second TBM ‘Elizabeth’ set to finish her drive by Autumn 2025.

At 65 hectares – the equivalent of 100 football pitches - Washwood Heath is one of HS2’s largest construction sites. Next to the tunnel portal, HS2’s Depot and Network Integrated Control Centre will also be built – acting the nerve centre of the high-speed rail network. From this site, trains will be serviced and stored and the real time operation of the railway will be controlled.

The site has also spurred the development of a 24 hectare brownfield site which will unlock land for commercial use and logistics space, creating opportunities for employers and the community, and more than 1,000 new jobs for local people.

Latest Construction News

28/05/2024

The UK's newest aggregate manufacturing plant has been officially opened in Wellingborough, providing low-carbon secondary aggregate to help meet the Midlands' construction needs. The plant will transform around 200,000 tonnes per year of incinerator bottom ash (IBA) left over from the ...
28/05/2024

City of Wolverhampton Council has announced that work has begun to erect the steel framework on a new city centre college campus as part of the council's transformational Phase Two City Learning Quarter masterplan. Situated around the Old Hall Street and St George's Parade area, incorporating a ...
28/05/2024

Network Rail engineers have installed two new lifts at Bridlington Station. Engineers worked to install two new lifts to the station's historic footbridge, making connections between platforms easier and more accessible. The bridge has also been given a new lease of life as Network Rail teams ...
28/05/2024

Mark Wild OBE has been appointed as the new Chief Executive of HS2 Ltd. He has been appointed to lead the completion of the high-speed railway and help realise its transformational benefits. As one of the most respected figures in the infrastructure industry, Mark brings almost four decades-worth ...
28/05/2024

Kier Group has scooped gold at the European Foundation for Management Development’s (EFMD) Excellence in Practice (EiP) awards for its talent development programmes. Kier has been working in partnership with Cranfield University to provide two programmes, Raising and Building Leaders, which ...
28/05/2024

Mecalac Construction Equipment UK has appointed Remi Tourtet as Global Sales Manager for Compaction and Dumper Equipment. Joining the business with immediate effect, the move demonstrates Mecalac's long-term commitment to continued commercial growth. With extensive senior level experience in ...
28/05/2024

SlatWall specialists Naturewall have expanded their waterproof collection with the addition of five new panels. This means homeowners have even more choice when it comes to choosing SlatWall for humid areas of the home. Plus, because each of these panels are low maintenance and easy to clean, they ...
28/05/2024

Heritage Cob & Lime are immensely proud of their bespoke lime mortar they made for the WaterAid ...
24/05/2024

Hull City Council and Caddick Construction have broken ground on-site to build 99 affordable homes at Dane Park Road, with handover due in Spring 2027. Upon completion, this upcoming residential area will consist of 20 one-bedroom, 49 two-bedroom, 20 three-bedroom and 10 four-bedroom homes, all ...
24/05/2024

Balfour Beatty has announced that it has been chosen by Rolls-Royce as its non-fissile construction partner to help deliver the expansion of its Raynesway site. Last June, Rolls-Royce revealed plans to double the size of its Submarines site in Derby to meet increased demand from the Royal Navy, ...
Think Construction Skills Ltd.JWCGo Geothermal LtdEfco UK LtdAqua Direct LtdLakeside HireBRICOFLOR UKACS Construction GroupTunley Rod & Bar Ltd1st Folding Sliding Doors
Terms and Conditions
2024/05/28 23:54:32