Network Rail is investing over £20 million to rebuild a major railway bridge that takes trains over the M62 in Castleton, near Rochdale.
Passengers and motorists are urged to check before they travel in September 2024 as rail and road closures are required to replace the 42m long, 2000 tonne bridge.
The work will ensure safe and reliable journeys for passengers and freight over this vital structure for years to come.
To complete the work, engineers need to dismantle the old bridge and take it away on the M62. The new bridge materials will be delivered by road and built on site.
The M62 will be closed over two weekends between J18 and J20:
• The evening of Friday 6 – early morning Monday 9 September
• The evening of Friday 20 – early morning Monday 23 September
Outside of the full road closure, the motorway will be reduced to three lanes. There will be nightly closures to support the work to the base of the bridge.
The railway will be closed 6-24 September between Manchester Victoria and Rochdale. Rail replacement buses will be in operation for passengers.
The bridge, known as Castleton bridge, carries 6% of the UK’s energy supply across the country, as freight trains carry material to and from Drax power station in Selby.
Olivia Boland, Network Rail sponsor, said: "The replacement of Castleton bridge is essential for the safe running of our railway, and crucial to the country’s economy as 6% of the UK’s energy supply relies on the bridge for transportation.
"I'd like to thank passengers and motorists for their understanding while we carry out this work. Please, check before you travel on the M62 or between Manchester and Rochdale in September 2024."