Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 157,206 companies....

Construction News

25/07/2023

Groundforce Shorco Supply Excavation For Thame Tideway Tunnel

Construction News Image
Groundforce Shorco has provided specialist Air Treatment Unit (ATU) excavation for the Thames Tideway Tunnel, as part of the ongoing Super Sewer project in London.

The project requires a number of ATUs to be installed along the route of the 25km tunnel, to treat exhausted air from the super-sewer.

Last year, Groundforce provided Costain, Vinci Construction Grands Projects and Bachy Soletanche Joint Venture on the Eastern section with sheet piles and a range of medium and heavy-duty bracing frames for the ATU excavation in the Deptford Church Street site.

Now, Groundforce Shorco is supporting another Tideway ATU excavation, this time at their Greenwich Pumping Station site.

This ATU excavation is especially challenging as it is in a very confined location, bounded on one side by Greenwich Pumping Station, a listed building, and on an adjacent side by an acoustic enclosure used by the JV to receive precast concrete tunnel sections for the Greenwich connection tunnel.

Civils Senior Engineer, Andrew Bellamy, said: "Although the ATU is only about 8m x 8m in plan, a sheet piled structure of 13m x 15m was designed to enable adjacent ventilation pipework and ducting to be installed simultaneously.

"Stringent limits on the deflection of the sheet were set due to the proximity of the excavation to the acoustic enclosure foundations, which includes a gantry crane, working continuously to supply the secondary lining works. The excavation was sheet piled on three sides, the fourth being the Grade 2 listed Thames Water pumping station."
-- Advertisement --
hss



Access to the acoustic enclosure needed to be maintained throughout the works, adding further restrictions to the already confined working area. The solution was to create a chamfer to one corner of the 14m x 13m x 5m deep excavation. This chamfer allowed articulated lorries to continue delivering materials.

Bellamy continued: "Due to the orientation of the site access gate it was physically impossible to move the vehicle route away from the ATU and without the chamfered corner vehicle access would have been completely impossible for HGVs."

Groundforce Shorco Area Manager Arpad Nagy added: "There are two excavators on site, including one 45-tonner, and three lorry deliveries per shift bringing tunnel segments for the tunnel boring machine which meant that our design had to accommodate an increased surcharge of 15kN/m2."

The excavation is lined with 6m-long GU13N steel sheet piles and braced with three levels of Groundforce's hydraulic Mega Brace frames. Four MP150 modular hydraulic props were installed as knee-braces (ie spanning the corners of the excavation) at all three levels within the excavation – a total of 12 props.

The MP150s are attached to brackets welded to the waling beams.

"These act as shear-stoppers to prevent the props sliding along the beams," explained Arpad.

One side of the excavation runs along the top of the pumping station's 10m-deep foundations.

"The JV had to drill into the foundation of the Grade 2 listed Thames Water pumping station in order to facilitate the installation of gallows brackets required to support the temporary frames," explains Arpad.

The support structure is designed to limit deflections in the sheet piles to within 10mm.

Designing the support system was complicated by the need to chamfer the corner of the excavation, says Arpad: "Once you lose that corner you need to recalculate the loadings and reposition the knee braces."

With the bracing installed, the 800mm-thick base slab was cast. When this had reached full strength, the two bottom levels of bracing could be removed to allow formwork to be assembled for the concrete wall lining.

The top level of bracing is due to be removed when the lining walls have reached 1m below ground level.

Despite the complexity of the job, design and installation of the support system has gone very smoothly.

"Groundforce have served us well on the ATU package, engaging at the design stage, attending site to deliver toolbox talks on the EMV, and generally with how the works were progressing," concluded Mr Bellamy.

Latest Construction News

16/05/2025
South Dock Marina in Southwark is set for a major £8 million overhaul aimed at improving health and safety across the site, following the recent approval of a redevelopment plan. Led by Southwark Council, the upgrade programme has been granted planning permission, pending further consultation with
16/05/2025
The South Rail Systems Alliance (SRSA) has completed a major programme of infrastructure upgrades on the West Anglia main line. Appointed in September 2023, the SRSA, comprising Colas Rail UK, Network Rail, and AECOM, delivered a package of works between Shepreth and Cambridge. This multidisciplina
16/05/2025
London Gatwick has announced a major partnership with renewable energy provider Vital Energi to deliver a £250 million decarbonisation programme, aimed at achieving net zero for the airport’s own emissions by 2030. Under a five-year contract, Vital Energi will help the airport transition away from
16/05/2025
Dale Turner, Director of Procurement and Supply Chain at Skanska UK, has been appointed Chair of the Supply Chain Sustainability School. Turner succeeds Shaun McCarthy OBE, who co-founded the School in 2012 and has led it since its inception. McCarthy will now transition into a roaming ambassador r
16/05/2025
Dudley's Aluminium has taken a major step in its journey to net zero by installing a large-scale solar energy system at its production facility in Cardiff. The company partnered with Inspire Green, a renewable energy specialist operating across south Wales and south-west England, to fit 192 high-ef
16/05/2025
If you're searching for architects in Tunbridge Wells, you're likely planning something exciting — from a home extension or renovation to a brand-new build. At Alex Bryla Architecture, we specialise in bespoke architectural design, offering a fresh and creative approach tailored to the uniq
15/05/2025
A major expansion of the Port of Tilbury has been set in motion as owners Forth Ports has submitted an outline planning application to Thurrock Council for the development of a new port facility, Tilbury3 (T3). The proposed project will redevelop a 100-acre brownfield site—equivalent to 70 football
15/05/2025
Morgan Sindall Construction has commenced work on a capital works programme at the University of Leeds campus. It was announced earlier this year that Morgan Sindall has been appointed to the programme, which will entail refurbishment of existing university spaces and entrances as well as reroofing
15/05/2025
Construction has officially begun on the long-awaited Marple Community Hub, a £20 million development that will bring a state-of-the-art leisure, health and library complex to the heart of Stockport. Local leaders, partners, and the main contractor Willmott Dixon gathered in Marple Memorial Park fo
15/05/2025
Great Places Housing Group recently welcomed senior leaders from Manchester City Council to tour the final phase of its flagship £19.4 million Wiremill Court development in New Islington. Council Leader Cllr Bev Craig and Cllr Gavin White, Executive Member for Housing and Development, visited the s
Efco UK LtdAqua Direct LtdLakeside HireStuart CanvasCompass Protection Manufacturing LimitedAqua Direct LtdAcuity ComplianceThe Bifolding Door FactoryAtspeed Steels & LintelsProcter Brother LTD