Contractor J Murphy and Sons is teaming up with Network Rail to replace the central spans of Nazeing New Road bridge from early January.
The work will require a four-month road closure and changes to train services.
The existing bridge sits over the West Anglia Main Line railway that carries trains between London and Hertfordshire, Essex and Cambridgeshire.
The condition and age of the bridge requires a regular maintenance and inspection regime to keep it safe for road and rail users. Despite remedial works being carried out between 2010-14, the bridge has continued to deteriorate and has reached the end of its useful life. It now needs to be fully replaced to avoid prolonged closure of this busy road across the railway. The new bridge is being designed to last 120 years.
The road will be closed from Tuesday 3 January 2023 until Sunday 30 April 2023 to allow the bridge replacement work to be completed. During this time, pedestrian and vehicle diversionary routes will be signposted.
The main work to remove the existing spans and install new ones will take place from Friday 13 to Wednesday 18 January inclusive. During these six consecutive days train services will be suspended and Greater Anglia has arranged rail replacement buses and ticket acceptance to allow passengers to complete their journeys.
Passengers should check before they travel through the Greater Anglia and National Rail websites, as well as other journey planning apps.
Gas, electricity and internet connections that run across the bridge have already been redirected over a temporary structure. This work was carried out during single lane closures earlier this year. These services will be installed through the new structure which will be done during the full road closure. No impact on local people’s use of these services is expected.
Ellie Burrows, Network Rail's route director for Anglia, said: "I'm sorry for the disruption that this work will cause to residents and rail users but if we don’t do this work now, it could lead to a much more disruptive closure at short notice. We’ve been working closely with community groups, local councils and schools to keep them informed of our plans and reduce the impact of the closure. Replacing the bridge will enable us to maintain a safe and reliable route for motorists, pedestrians and rail users for years to come."
Construction News
25/11/2022
Central Spans Of Nazeing New Road Bridge To Be Replaced


30/06/2025
Places for London, Transport for London's wholly owned property company, has announced Ballymore as its joint venture partner for the transformation of the Limmo Peninsula in east London.
The partnership will see the creation of around 1,400 new homes, spanning affordable, market, and rental tenur

30/06/2025
Balfour Beatty, in partnership with Laing O'Rourke and Bouygues Travaux Publics, has officially signed the Programme Alliance Agreement with Sizewell C to deliver the main civil works at the UK's next nuclear power station.
The three companies will operate as the Sizewell C Civil Works Alliance (CW

30/06/2025
Morgan Sindall Construction and Southampton City Council have officially broken ground on the £36 million transformation of the city's historic Outdoor Sports Centre, marking a major milestone in one of the region's most ambitious regeneration projects.
A ceremonial event to celebrate the start of

30/06/2025
Doncaster Council has officially received a new collection of affordable homes at the Nutwell Grange development in Armthorpe, as part of a housing partnership with housebuilder Persimmon.
Deputy Mayor Glyn Jones and Councillor Majid Khan visited the site this week to mark the handover of eleven on

30/06/2025
Winvic Construction Ltd has announced the shortlisting of seven awards at this year's prestigious 'Inspiring Women in Construction and Engineering Awards' (IWCE).
The shortlist celebrates both individual excellence and Winvic's company-wide commitment to advancing equity and inclusion in the built

30/06/2025
Alder Hey Children's Hospital and construction partner Morgan Sindall are celebrating a significant milestone in the development of a new facility that promises to transform care for children and young people.
The structure of the new building, which will house a state-of-the-art surgical neonatal

30/06/2025
Henry Boot PLC has announced that its land promotion and planning arm, Hallam Land Management, has completed the sale of a freehold site in Yalding, Kent, to housebuilder Fernham Homes.
The site has full planning permission for 112 residential units.
The sale has generated an ungeared internal ra

30/06/2025
A St Mungo's care home in Islington for people affected by homelessness has reopened its doors after a transformative refurbishment delivered by volunteers from delivery consultants and construction specialists Mace.
The six-week project, led by 46 Mace volunteers, saw the complete redesign and re-

30/06/2025
Galliford Try has marked a key construction milestone at its flagship project, The Rise, with a topping out ceremony celebrating the completion of the building’s structure at Guildford Crescent in the heart of Cardiff.
Once completed, The Rise will become Cardiff's tallest building, delivering 272

30/06/2025
Thousands more young people in the North East will be trained for careers in the fast-growing green energy sector thanks to an £8.48 million investment approved by North East Mayor Kim McGuinness and her Cabinet.
The funding will support the expansion of Newcastle College's Energy Academy in Wallse