G F Tomlinson has completed construction work on the £3.9million expansion and renovation of King Edward VI School in Lichfield, Staffordshire.
Delivered on behalf of Staffordshire County Council, under the Staffordshire Construction framework, the works comprised of an extension to an existing building and the construction of a new modular building for the school.
Construction works at the co-educational comprehensive began in May 2020, and the extension and refurbishment will now allow the school, which takes on pupils aged 11 to 18, to increase its intake by 30 places a year, providing an additional 150 places in total.
The new three-storey extension, which was phase one of the works, was constructed on the site of a former swimming pool that had been closed for over ten years. It now houses enhanced teaching and auxiliary spaces, as well as an administration area on the lower ground floor that features a new student services area.
Phase two, which completed in October last year, involved the installation of a brand new standalone modern modular structure to provide enhanced science laboratory teaching facilities, which replaced existing accommodation and obsolete prefabricated buildings at the site.
Due to the scheme being completed by the contractor on time and to budget, G F Tomlinson was awarded further refurbishment works at the school, which included window replacements in the main hall, as well as new windows, ceilings, floors and interactive whiteboards in a number of classrooms.
The contractor also provided external works as an add on to the original scheme which included new railings, fencing, outdoor steps and re-surfacing works.