A preferred bidder has been selected to deliver the Silvertown tunnel in East London, connecting the Greenwich peninsula and the Silvertown district.
The RiverLinx consortium - comprising Aberdeen Standard Investments, BAM PPP PGGM, Cintra, Macquarie Capital and SK E&C - will design, build, finance, operate and maintain the tunnel under a £1 billion contract.
Transport for London (TfL) began a competitive bidding process in March 2016, with bidders shortlisted in March 2017 and a final decision in May 2019.
Design and construction of the project will be delivered by a consortium of BAM Nuttall (including sister company Wayss & Freytag Ingenieurbau providing specialist tunnel engineering expertise), Ferrovial Agroman and SK E&C.
The design includes a 1.4-kilometre twin-bore road tunnel under the River Thames as well as 0.6-kilometres of access ramps. It will also be located within the extended Ultra Low Emission Zone (ULEZ) which from October 2021 will mean any vehicles not meeting strict emission standards will have to pay an additional ULEZ charge to TfL to use the tunnel once it's open.
The catchment area of the new Silvertown Tunnel is expected to see a projected population increase of 650,000 people and see an estimated 286,000 new jobs created by 2036.
The new infrastructure will serve as an alternative to the Blackwall Tunnel, improving traffic flows not only under the River Thames but also in the approaches between Docklands / East London and Southeast London.
The new tunnel will also significantly improve cross-river public transport connections. There is currently only one cross-river bus link in East London due to the lack of suitable crossings. However, the Silvertown project will provide a dedicated bus lane in either direction. The current number of buses which cross the river at this location will increase to 37 buses an hour in each direction - all of which are expected to be zero emission from launch.
By significantly reducing local congestion, using access tolls to encourage sustainable transport modes and increasing public transport provision the project will have a significant beneficial impact on local air quality. The tender requirements will require Riverlinx to undertake comprehensive improvements to the existing urban environment either side of the river, enhancing public spaces and promoting more walking and cycling.
The commercial and financial close of the project are expected later this year, after which construction will commence.
It will run for twenty-five years beyond construction, with RiverLinx responsible for the operation and maintenance of the project.