Construction equipment supplier Groundforce is providing its large hire fleet for a major water infrastructure project in Glasgow.
Scottish Water is building a 3.1 mile-long waste water tunnel in the south of Glasgow as part of the biggest upgrade of the city's waste water network in more than a century.
The Shieldhall Strategic Tunnel, which will run between Craigton and Queen's Park area of Glasgow, forms part of a £250 million, five-year programme of work to upgrade the waste water network in the Greater Glasgow area.
The scheme is the biggest investment in Glasgow's waste water network since Victorian times and is designed to handle increased rainwater flows and improve water quality in the River Clyde and its tributaries.
The 4.7m diameter Shieldhall Strategic Tunnel is a vital link in this upgraded sewer network. Under construction by Costain Vinci JV (a joint venture of Costain and Vinci Construction Grands Projects) the tunnel is mostly developed using a tunnel boring machine (TBM).
The tunnel begins and is launched in Craigton with Costain Vinci JV is using a cut-and-cover method of tunnel construction, with this section of tunnel, extending some 190m in length, is being constructed in an excavation approximately 8m deep and 5.7m wide, within contiguous concrete bored pile retaining walls.
The construction method involved sinking the piles, then excavating the first metre or so before installing temporary works to withstand the lateral forces and prevent the piled walls collapsing as the excavation was dug to its final depth. The temporary support was required to remain in place while Costain Vinci JV cast the tunnel invert.
Groundforce was awarded the hire contract for equipment to provide this support. The company proposed a system comprising of its modular Megabrace beams installed as a continuous waling beam braced with MP125 hydraulic props spanning the excavation.
Costain Vinci JV site manager Ian Bowley said: "The original plan was to excavate in sections, casting the tunnel invert before striking the temporary supports and 'leap-frogging' along to the next section. But we re-phased the operation so that the excavation progressed more quickly than originally planned."
The new arrangement meant that instead of the excavation being opened in sections, the entire 190m-long trench was excavated at once. This accelerated the programme, but in order for this method to work, Groundforce had to ensure that it could supply enough equipment to support the entire 190m excavation. The original plan was to supply sufficient support for no more than 60% of the excavation at any one time.
The support system designed by Groundforce comprised two levels of Mega Brace waling, one approximately 0.75m from the top of the contiguous piles, the other at the bottom of the excavation, approximately 4.5m below.
In total, this arrangement required about 720m of Mega Brace and 112 props to be supplied.
Groundforce Major Projects Manager, Mark Whitmore, said: "This meant that we had to divert some of the hire fleet to Shieldhall and manufacture additional props to avoid shortfalls elsewhere."
Mega Brace beams can span substantial lengths, but the majority of the units employed at Shieldhall were 7m long. The reason for this was that instead of following a straight line, the excavation is curved, following a radius of 150m. Long beams would describe a chord, creating wide segments across the radius of the curve. This would have the effect of narrowing the excavation and creating gaps between the bracing and the piled retaining wall that would need substantial packing.
Using more, but shorter, beams allowed the curve to be followed more smoothly, minimising the size of these gaps and requiring minimal packing to distribute the loads evenly. Each Mega Brace beam was supported with an MP125 hydraulic prop at either end and the beams were located and supported vertically by bespoke gallows brackets bolted into the concrete piles.
An additional complication was that, due to this curve, the outer side of the frame had to be marginally longer than the inner side. This was accomplished by assembling the waling beam so that nine of the 27 bays incorporated 7.5m Mega Brace beams to provide the extra 4.5m of waling beam to accommodate the larger outer radius.
As one of the UK's leading specialists in the hire of temporary works equipment, Groundforce was able to offer the Costain Vinci JV a turnkey service which involved the supply of a temporary bridge to span the open excavation.
Installed in January 2016, two months after installation of the trench support system, this comprised an 8m modular bridge with protective canopy that follows the line of an existing footpath that provides access to a pedestrian underpass underneath the adjacent M8 motorway.
Groundforce Bridge Manager, Terry Mead, added: "The contractor required a pedestrian bridge with a roof to ensure additional safety for personnel. Groundforce Bridge designed and fabricated a unit specifically for this project."
This section of project will be completed in Q3 2016, with the tunnel completion set for early 2018.
www.vpgroundforce.com
Construction News
09/08/2016
Groundforce Provides Hire Fleet For Glasgow Shieldhall Tunnel Project


16/06/2025
Construction is underway on Siemens Mobility's new £20 million Bogie Assembly and Service Centre in Goole, with Yorkshire-based contractor Caddick Construction leading the build.
The 13,500 sq m facility will form a key part of Siemens Mobility's expanding Goole Rail Village and is set to boost the

16/06/2025
Construction has officially been completed on Molson Coors Brewing Company's new UK headquarters in Burton-on-Trent, delivering a state-of-the-art 10,300m² facility to support the brewer’s expanding operations across the UK and Ireland.
The project, led by main contractor Clegg Food Projects, invol

16/06/2025
Equans has signed a new five-year Strategic Partnership agreement with Cheshire West and Chester Council to deliver facilities management services across the Council’s estate.
The deal follows the conclusion of a previous joint venture between the two parties, known as QWEST, which had been operati

16/06/2025
Winvic Construction Ltd has been appointed by Guildford Borough Council to deliver a major package of highways infrastructure works for the Weyside Urban Village, a landmark regeneration project that will bring 1,550 new and affordable homes to the area alongside green spaces, employment zones, a co

16/06/2025
Real estate developer TT Group has received planning approval from Stoke-on-Trent City Council to convert the former Telecom House office building in Hanley into 99 residential units.
The seven-storey, 103,000 sq ft property on Trinity Street was previously occupied by BT and has remained vacant. T

16/06/2025
Foundation engineering specialist Roger Bullivant Limited (RBL) is making significant progress on the Balderton Rise residential development in Newark, working in partnership with housing provider Lovell.
The current phase of the project includes 102 new homes and highlights RBL’s commitment to su

16/06/2025
NHS Shared Business Services (NHS SBS) has launched the third iteration of its Modular Buildings framework agreement, designed to accelerate the delivery of vital infrastructure projects across the UK in healthcare, education, housing, and other public services.
The new Modular Buildings 3 framewor

16/06/2025
Network Rail has successfully completed a major £84 million upgrade to overhead line equipment (OLE) on the Midland Main Line between London St Pancras and Bedford — delivering the project on time and under budget.
The OLE125 Compatibility project, which ran from September 2023 to June 2025, replac

16/06/2025
Kier has completed the delivery of a major new life sciences facility at the Advanced Research Clusters (ARC) West London Refinery Building in Hammersmith, providing 150,000 sq ft of high-specification laboratory, research and development space.
Situated on the northern embankment of the River Tham

16/06/2025
Esh Group has been recognised as one of the UK's Best Managed Companies 2025, earning a place among just ten private businesses selected nationally for the prestigious accolade.
The award, presented through Deloitte Private's Best Managed Companies programme, honours outstanding organisational perf