Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 146,423 companies....

Construction News

09/08/2016

Groundforce Provides Hire Fleet For Glasgow Shieldhall Tunnel Project

Construction equipment supplier Groundforce is providing its large hire fleet for a major water infrastructure project in Glasgow.

Scottish Water is building a 3.1 mile-long waste water tunnel in the south of Glasgow as part of the biggest upgrade of the city's waste water network in more than a century. 

The Shieldhall Strategic Tunnel, which will run between Craigton and Queen's Park area of Glasgow, forms part of a £250 million, five-year programme of work to upgrade the waste water network in the Greater Glasgow area.

The scheme is the biggest investment in Glasgow's waste water network since Victorian times and is designed to handle increased rainwater flows and improve water quality in the River Clyde and its tributaries.

The 4.7m diameter Shieldhall Strategic Tunnel is a vital link in this upgraded sewer network. Under construction by Costain Vinci JV (a joint venture of Costain and Vinci Construction Grands Projects) the tunnel is mostly developed using a tunnel boring machine (TBM).

The tunnel begins and is launched in Craigton with Costain Vinci JV is using a cut-and-cover method of tunnel construction, with this section of tunnel, extending some 190m in length, is being constructed in an excavation approximately 8m deep and 5.7m wide, within contiguous concrete bored pile retaining walls.

The construction method involved sinking the piles, then excavating the first metre or so before installing temporary works to withstand the lateral forces and prevent the piled walls collapsing as the excavation was dug to its final depth. The temporary support was required to remain in place while Costain Vinci JV cast the tunnel invert.

Groundforce was awarded the hire contract for equipment to provide this support. The company proposed a system comprising of its modular Megabrace beams installed as a continuous waling beam braced with MP125 hydraulic props spanning the excavation.

-- Advertisement --
hss

Costain Vinci JV site manager Ian Bowley said: "The original plan was to excavate in sections, casting the tunnel invert before striking the temporary supports and 'leap-frogging' along to the next section. But we re-phased the operation so that the excavation progressed more quickly than originally planned."

The new arrangement meant that instead of the excavation being opened in sections, the entire 190m-long trench was excavated at once. This accelerated the programme, but in order for this method to work, Groundforce had to ensure that it could supply enough equipment to support the entire 190m excavation. The original plan was to supply sufficient support for no more than 60% of the excavation at any one time.

The support system designed by Groundforce comprised two levels of Mega Brace waling, one approximately 0.75m from the top of the contiguous piles, the other at the bottom of the excavation, approximately 4.5m below.

In total, this arrangement required about 720m of Mega Brace and 112 props to be supplied.

Groundforce Major Projects Manager, Mark Whitmore, said: "This meant that we had to divert some of the hire fleet to Shieldhall and manufacture additional props to avoid shortfalls elsewhere."

Mega Brace beams can span substantial lengths, but the majority of the units employed at Shieldhall were 7m long. The reason for this was that instead of following a straight line, the excavation is curved, following a radius of 150m. Long beams would describe a chord, creating wide segments across the radius of the curve. This would have the effect of narrowing the excavation and creating gaps between the bracing and the piled retaining wall that would need substantial packing.

Using more, but shorter, beams allowed the curve to be followed more smoothly, minimising the size of these gaps and requiring minimal packing to distribute the loads evenly. Each Mega Brace beam was supported with an MP125 hydraulic prop at either end and the beams were located and supported vertically by bespoke gallows brackets bolted into the concrete piles.

An additional complication was that, due to this curve, the outer side of the frame had to be marginally longer than the inner side. This was accomplished by assembling the waling beam so that nine of the 27 bays incorporated 7.5m Mega Brace beams to provide the extra 4.5m of waling beam to accommodate the larger outer radius.

As one of the UK's leading specialists in the hire of temporary works equipment, Groundforce was able to offer the Costain Vinci JV a turnkey service which involved the supply of a temporary bridge to span the open excavation.

Installed in January 2016, two months after installation of the trench support system, this comprised an 8m modular bridge with protective canopy that follows the line of an existing footpath that provides access to a pedestrian underpass underneath the adjacent M8 motorway.

Groundforce Bridge Manager, Terry Mead, added: "The contractor required a pedestrian bridge with a roof to ensure additional safety for personnel. Groundforce Bridge designed and fabricated a unit specifically for this project."

This section of project will be completed in Q3 2016, with the tunnel completion set for early 2018.

www.vpgroundforce.com

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Lakeside HireBRICOFLOR UKPro Structures LtdCeildoor Products LimitedMezzanine Floor Engineering LtdMayfair Steel BuildingsAllcott CommercialSEEIT3DBAM Construction Training LtdTuffshop - HiVIs Protective Clothing