28/04/2014

Steelwork Innovation At Wastewater Treatment Plant

The innovation of modular steelwork is making the construction of a major wastewater treatment plant in Liverpool safer, faster and more cost effective.

GCA (Galliford Try, Costain & Atkins) JV is building the UK's first multi-storey CASS (Cyclic Activated Sludge System) sequencing batch reactor (SBR) plant in partnership with United Utilities.

"To innovate the steelwork installation, we had to challenge the traditional methods – how could we make it safer and faster but at the same time improve quality?" said Alistair Smithyman, Design Coordinator on the project.

The team decided on modular construction, where an area or section of the works arrives to site in a pre-assembled state, ready for lifting into position.

-- Advertisement --
hss

This has the benefit of greatly reducing site installation time and increases site safety by reducing exposure to working at height. The quality of the product is superior as it is assembled in factory conditions; any modifications can be undertaken before it comes to site, with no site welding required.

Costs are competitive; although generally modularisation requires additional steel to make the scheme work, this is offset by reduced transportation costs, labour and crane requirements for the erection.

This innovation was kick-started by the design and installation (with Supply Chain Partner Peers Ltd) of the high-level decanter cover steelwork platform. The platform was an expanse of 2800m2, sitting at the top of the SBR (18m above ground floor level), with 7m open drops to the basins below.

The issue of working at height and restrictive access conditions meant that alternative and innovative installation methods needed to be used. The platform was split into eight areas, (approximately 350m2 each). Each area was then split into 14 separate modules. Each module was delivered to site and installed in a completed state, inclusive of all handrailing and edge protection to ensure working at height needs were minimised. Each area took a total of two days to install and complete.

(CD)

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
BRICOFLOR UKLakeside HirePro Structures LtdHBB GeoSales LtdConservatory Roof InsulationRenderplas LtdCeildoor Products LimitedIndustrial Spray Concepts LtdGreen Home Energy (Private) LimitedWaverley