Costain Completes Waste Work One Year Early

Costain has completed work on the refurbishment of Severn Trent Water (STW)'s Kineton waste water treatment plant near Coventry twelve months ahead of schedule.

The Kineton Q project involved revamping the site’s process assets to enable it to comply with lower EU ammonia discharge consent levels. These do not come into force until March 2015, however there was a small risk that the chosen solution might not deliver the required outputs to satisfy the new consent. The STW/Costain team decided to take a risk based approach and carry out the work as early as possible so it had time to react if the scheme was unsuccessful. In order to undertake the refurbishment work the process would have needed temporary treatment units to help prop up the site whilst the NSAF (Nitrifying Submerged Aeration Filter) was out of commission. However the team made use of the seasonal relaxation of consent levels for this site from November to April to undertake the work, so that no temporary treatment was required.

-- Advertisement --
hss

Richard Price, Costain Programme Manager, said: "The Environment Agency relaxes consents for some sites in the winter when conditions are wetter and the concentration of ammonia in the waste is lower. In summer, conditions tend to be drier, the concentrations higher and so the consent is tighter.

"Carrying out the work in winter meant we did not have to install a temporary filter. Instead we just had to isolate the NSAF while we refurbished the plant’s media. This new approach allowed us to complete the physical works in less than a week, saving us a significant amount of time. Because the work was completed a year early we could also trial a lower cost option that did carry some risk of failure. We had the time to react if the solution did not work."

By assisting the Severn Trent Water process engineers with sampling and testing, the Costain team was able to handover the process in less than two months.

(CD)

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Pro Structures LtdLakeside HireBRICOFLOR UKA1 SurveyBPC VentilationLees Logistics LimitedThe ThreadmakersAdvanced Chemical Specialties Ltd.Jackson Coldroom Services LtdCuchulainn Workwear