Costain Skanska JV Complete Diaphragm Walls And Columns

Crossrail contractor Costain Skanska Joint Venture (JV) has completed the construction of the diaphragm walls and columns that will support the roof of the new Crossrail Paddington Station.

Work started on the project in April 2012 to construct a 40 metre deep reinforced concrete wall around the perimeter of the new station. Crossrail, Costain Skanska JV and subcontractor Cementation Skanska worked round the clock for 11 months to put in place the 165 individual diaphragm wall panels and 51 plunge columns to form a box 265 metres long and 22.5 metres wide.

The completed walls, which are made up of 165 rectangular panels measuring 3.3 metres in length, 1.2 metres in width and 40 metres deep, required over 64,000 tonnes of concrete and 5,000 tonnes of steel in their construction. The excavation of the panels saw over 53,000 tonnes of London clay removed.

-- Advertisement --
hss

The project wasn't without its challenges, particularly due to the restricted space the site team had to work in. The tunnel boring machines that are being used to construct the new train tunnels had to pass through the walls of the station as part of their journey between Royal Oak and Farringdon, which meant the team had to meet tight deadlines. Each boring machine measures 150 metres long - roughly equivalent to 14 London buses placed end to end - and weighs around 1,000 tonnes.

"One of the biggest challenges we encountered was completing the required minimum proportion of wall ahead of the approaching tunnel boring machines. A failure to get this done on time would have meant serious delays elsewhere on the programme," said Rupert Shingleton, Costain's Project Director.

After the outer walls were completed, the team then put in place 60 metres by 1.8 metres diameter central columns to support to the station roof and provide ground anchorage to the box.

The new Crossrail Paddington Station will be 260 metres long, 30 metres wide and 30 metres deep and will provide step free access to platform level along with an interchange with National Rail and London Underground. Eastbourne Terrace, a main road that serves Paddington Station, will be reopened once the work has finished, with a target date set for February 2014.

(CD)

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
BRICOFLOR UKPro Structures LtdLakeside HireNormac Oils LtdSheridan Group LtdStuart CanvasCounty Flat Roofing (UK) LimitedPremier Lift Group UKPlantcraft LtdNeil Vessey Storage Tanks Ltd