Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 146,423 companies....

Construction News

05/04/2013

World's Second Deepest Sewage Treatment Works Takes Shape In Jeddah

Contractor Abuljadayel Co., specialists in the field of water and waste water projects, has utilised a number of formwork and shoring solutions provided by RMD Kwikform to support the construction of the World's second deepest pumping station at the North Jeddah Pumping Station project in Saudi Arabia.

Designed to deal with the increased demands of the growing population of Jeddah, the new facility is part of a $1.1bn investment programme funded by Saudi Arabia's National Water Company. The North Jeddah pumping station facility comprises of a screen shaft and two pumping shafts, all of which drop over 72 metres in total into the ground. There is also a three-stage collection chamber, various auxiliary buildings and permanent site offices.

Each shaft is 68 metres deep. The screen shaft has a 4.5 metre thick concrete base slab and each pumping shaft has a 5.5 metre thick base slab. Before RMD Kwikform started supplying formwork, the contractor constructed the circular diaphragm walls using 2.4 metre concrete panels. Once excavated to full depth, the 1.2 metre shaft thick wall was constructed, followed in succession by the bottom slab.

There were three main formwork elements of the project that RMD Kwikform was involved in, including supplying double-sided wall formwork to the U-shaped Collection Chamber building. Using a range of equipment, including steel Superslim Soldiers as primary beams and Alform beams as secondaries, the wall formwork reached a total height of 13 metres. With 348 linear metres of equipment being used for this section of the construction, the entire structure above ground level was poured in a single pour, using a total volume of 3,100m3 of concrete.

Rapidshor shoring with U-heads and Alform beams were also used to support 500mm thick concrete slabs on top of the three 46 metre diameter shafts. The Rapidshor was built 68 metres high and topped with U-heads, which held double Alform beams as primary bearers and single Alform beams as secondaries.

Commenting on the project, Mohammed Asif from RMD Kwikform said: "When we were faced with the shoring challenge of supporting a slab 68 metres high, but underground in a confined space with very little room to play with, we recognised there were two key hurdles to the project, the first being safety and the second logistics. Having had previous experience using Rapidshor on major bridge projects, we knew the equipment was structurally capable of dealing with the load, and due to it being a modular system, installation was more straightforward within the confines of the shafts."

-- Advertisement --
hss

In order to support the slab construction, each shaft was lined with over 10,255m3 of Rapidshor shoring. This was built up into a birdcage structure, securely tied into the main concrete walls and laced together to form a shoring solution capable of supporting the construction of drop beams and the capping slab of each shaft.

The 2,000mm deep, 600mm wide, 5,000mm long drop beams were constructed using Superslim Soldier primary beams and Alform secondary beams, with the slab support constructed using Alform beams. The 500mm deep capping slabs were then poured in order to partially cover the shafts. The cover slabs will go on to form part of the ground floor of permanent site offices, due to be built towards the end of the project.

Mohammed Asif continued: "The main engineering challenge was how to tie the system together and install safe access for the workers. It was for this reason that as part of the solution we supplied onsite technical assistance in the shape of two site operatives. One of the technicians remained onsite with the ground team from start to finish, with an additional team member supporting the training and erection programme devised for the customer."

The third part of the construction that RMD Kwikform assisted with was to supply a Rapidclimb and Maxima wall formwork panel system for the 500mm thick internal walls, required for the lift core walls, stairwells and offices for two of the shafts. In order to provide an efficient and safe solution, RMD Kwikform recommended a combination of Maxima modular wall formwork and Rapidclimb climbing formwork. The panel system approach was specified by the contractor, having seen the capabilities of Maxima.

The RMD Kwikform Rapidclimb system was used inside two of the pumping shafts to provide wall formwork to the lift-shaft cores and internal walls. Rapidclimb is a crane assisted climbing formwork system that provides safe, self-contained working levels for economical core and wall forming. It also features a rack and pinion activated mechanism with a wedge-locking device for securing the position of the shutter. The climbing bracket can achieve up to 45kN maximum vertical capacity.

Mohammed Asif commented: "When we were faced with the core formwork challenge, we saw it as an opportunity to utilise the capabilities of Maxima as the wall formwork system. It has been used extensively in similar projects across the globe, so we were confident it was the right solution to overcome the challenges posed by this project.

"By reusing the Maxima panels for each of the 24 pours required for the formation of the core, significant time and cost saving benefits were realised. Mohammad Rateb Jawish from Abuljadayel Co. said: "The tight programme time required us to think carefully about the solution we required for the formwork and shoring parts of the project. Using a modular panel system, such as Maxima allowed us to complete the whole core construction efficiently and to a high quality standard. The time and cost saving benefit we saw certainly showed the advantages of utilising a panel systems on this type of project."

Construction is expected to be completed in June 2013. Once operational, the Pumping station is designed to pump a maximum flow of 1,125,000m3 per day, ensuring enough capacity to cope with future predictions for population growth.

formula.rmdkwikform.com

Latest Construction News

24/07/2026
Planning approval has been granted for the redevelopment of the Crystal Palace National Sports Centre (CPNSC), marking a major milestone in securing the long-term future of one of the UK's most significant sporting venues. The decision allows the project to move forward to the next phase, creating
Read More
24/07/2026
Designer Group has been appointed to carry out the mechanical and electrical (M&E) works for the redevelopment of West One in London, a major refurbishment and rebuild located above Bond Street Underground station. Originally developed in the late 1970s, the existing West One Shopping Centre is bei
Read More
24/07/2026
The London Irish Centre has appointed Sisk, one of Ireland and Britain's leading construction firms, as the main contractor for the £36–£38 million transformation of its home at 50–52 Camden Square. Work is due to start in early 2027 and the centre is planned to reopen in Q1 2029, marking a major s
Read More
24/07/2026
Network Rail has confirmed that Botley Road in Oxford will remain closed beyond the end of August, delaying the previously planned reopening agreed when the programme was revised in January 2025 to prioritise getting traffic moving again. During recent drainage excavation for the new road layout, t
Read More
24/07/2026
Network Rail and The Arch Company have agreed a multi-million-pound transaction to transfer a selection of London property assets into Arch Co's ownership, marking a further milestone in their ongoing partnership. The package comprises a mix of railway arches and other investment properties — inclu
Read More
24/07/2026
More than 100 builders came together in Oxfordshire for the FMB's National Conference, which doubled as a milestone celebration of the Federation's 85 years supporting the trade. Staged on 9–10 July at the Oxford Belfry Hotel & Spa, the event welcomed 156 delegates for a Business Conference under t
Read More
24/07/2026
Established in 1996, The Access Flooring Company—distinguished from copycat businesses—marks three decades of excellence by reinforcing its position as the UK's premier specialist in raised access flooring, raised floor configurations, and advanced pedestal floor system technologies. Marking its la
Read More
24/07/2026
NFRC is urging members to help shape a new Government strategy for built environment professions, as the sector adjusts to the Building Safety Regime and renewed expectations on competence, professionalism and accountability. NFRC recently took part in a Build UK forum with the Building Professions
Read More
24/07/2026
Fire safety in homes and buildings is under closer scrutiny than ever. Whether you’re replacing a door, adding a glazed screen or partitioning a space, using the correct fire-rated glass is essential. The Glass Shop Online supply certified fire-rated glass and help customers navigate the requiremen
Read More
23/07/2026
Mace Consult has been appointed across six lots of Transport for London's (TfL) Professional Services Framework 3 (PSF3), strengthening a long-running collaboration and positioning the firm as a leading delivery partner on major infrastructure across the capital. Under the framework, Mace Consult w
Read More
Pro Structures LtdLakeside HireBRICOFLOR UKGMS Ltd.Morgan Ellis LiftsArmour Industrial Doors LtdRatio RecruitmentGrade 1 hiregrade 1 hire -   Temporary Edge Protection for Stairs & Landinggrade 1 hire - access towers, podiums and pther access equipment.