09/11/2012

Main Phase Of Utility Works To Begin For New Farringdon Station

Construction News Image
As part of the construction of the new Farringdon station, Crossrail needs to protect and replace the utilities that lie beneath Farringdon Road.

The preparatory works began in August this year, with the main phase of the utility works commencing on Monday 12 November. The works are expected to continue until May 2013.

A number of water, gas and other utility pipes that run under Farringdon Road, must be replaced or monitored as they could potentially be affected by ground settlement caused by station and tunnelling works.

A major benefit of the works is that, once complete, the major local utilities will have been replaced or upgraded which will significantly reduce the level of utility works on Farringdon Road in future years.

Crossrail has been working closely with the utility companies, Transport for London (TfL), the London Boroughs of Camden and Islington and the City of London to minimise the impact of this work for businesses, shoppers and local residents.

-- Advertisement --
hss

To minimise future works in the Farringdon area, TfL will coordinate with other companies who have assets in the road that may need repairing or replacing.

These utility works will require a southbound closure of Farringdon Road between Clerkenwell Road and Charterhouse Street from 12 November 2012 to April 2013.

Southbound traffic will follow a signed diversion from Farringdon Road along Rosebery Avenue, Gray’s Inn Road, High Holborn, Holborn Circus and Charterhouse Street.

For cyclists, a southbound cycle-lane will be put in place in the closed section of Farringdon Road. This contra-flow lane will be segregated from northbound traffic. This means that cyclists will not need to use the diversion route.

London Buses route 63 southbound services will be affected by this diversion. Passengers for Farringdon station should alight at Snow Hill bus stop. Northbound buses, towards King’s Cross will be not be diverted. Bus stop 'A' at Farringdon station, will be closed for the duration of the works.

The three pedestrian crossings over Farringdon Road within the closed section will remain in operation at all times. These are at the junctions with Charterhouse Street, Cowcross Street and Clerkenwell Road.

Farringdon is at the heart of the Crossrail route and will be a key link in bringing passengers directly from within Greater London and beyond to the business hubs in the City and Canary Wharf. Located at the only intersection between Crossrail and Thameslink, Farringdon will directly connect with three of London's five airports, providing a railway connection between Heathrow and Gatwick. When complete, over 140 trains per hour will flow through the Farringdon interchange.

(CD)



Latest Construction News

03/05/2024

Construction firm GRAHAM has started building work on a £19 million Community Diagnostic Centre (CDC) in Workington town centre. The Centre will be located next to Cumberland Council's government-funded Innovation Hub which is also under development in Central Way. GRAHAM is the principal ...
03/05/2024

Significant progress is being made on a new £2 million recycling centre in Haverhill. Construction works are being completed by FCC Environment and its contractor DXI Regeneration Ltd, on behalf of Suffolk County Council. The facility will be operated by FCC Environment, which manages all of ...
03/05/2024

Midlands contractor G F Tomlinson has started work on a new primary school in Dunstall Park Estate, Tamworth. The work is taking place on behalf of Staffordshire County Council alongside project managers and concept architects, Entrust. The project was procured through the Constructing West ...
03/05/2024

Galliford Try has made another step in its carbon reduction journey with the deployment of a new digital platform across its Infrastructure projects. The platform, Qflow, automates data capture and processing by extracting information from delivery and waste tickets, using Artificial Intelligence ...
03/05/2024

Underfloor heating is the most efficient method of heating a room and is fast becoming the most popular option for new building and property refurbishments. As a result, more trade professionals are being asked to install underfloor heating and self-builders and renovators are using it as their ...
03/05/2024

Farrans is making significant progress at Barsham Water Treatment Works in Suffolk, where its client Essex and Suffolk Water is investing more than £49 million in upgrades to the site. Due to be complete in 2025, the project will provide improvements to the resilience and quality of drinking ...
03/05/2024

Work has been completed on a new bridleway bridge at Lindsells Level Crossing in Biggleswade, Bedfordshire. Work started in December 2022 on the fully accessible bridleway bridge which allows pedestrians, horse riders, cyclists and other users to safely cross the railway line, providing better ...
03/05/2024

Ideal Work UK has unveiled Microtopping®, a revolutionary cementitious coating that delivers the sleek, sophisticated look of polished concrete with unparalleled versatility and ease of application. ...
03/05/2024

Building work has commenced on a new development in Oundle that will bring self-contained extra care apartments to the area along with 62 homes and three self-build plots. Persimmon's East Midlands team have started preparing the Barnwell Walk site off St Christopher’s Drive in the town and expect ...
03/05/2024

Morgan Sindall has been appointed to two new Pagabo frameworks. The two frameworks are valued at £1.6 billion each and will run for four years. It was confirmed earlier this month that Morgan Sindall had been appointed to the new £1.6bn Healthcare Decarbonisation Framework from Pagabo, which has ...
Efco UK LtdAqua Direct LtdThink Construction Skills Ltd.JWCBRICOFLOR UKLakeside HireAsk EngravingMilestone FlooringArdent Consulting EngineersAM Bristol Electrical Services
Terms and Conditions
2024/05/05 15:19:57