Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
25/07/2012

Construction Of New Docklands Tunnel Shafts Near Completion

Construction News Image
Significant progress continues to be made at Crossrail's major tunnelling site in east London ahead of work commencing on the eastern tunnels between Docklands and central London.

Workers have now reached the temporary bottom of the two huge launch shafts where tunnel boring machines will be lowered into ahead of tunnelling commencing. The larger of the two shafts is 30 metres in diameter and will be 44 metres deep when completed. Construction has now commenced on two mined tunnels that will connect the two shafts.

Assembly of Crossrail's third tunnel boring machine (TBM), Elizabeth, is now well underway. The large blue cutterhead was installed earlier this week with the TBM now visible from the Docklands Light Railway. During the coming months, the 150 metre machine will be fully assembled and tested before being lowered in sections into the two shafts.

-- Advertisement --
hss

Over 250 people are now working at the Limmo Peninsula site with that number expected to peak at around 500 people at the height of construction.

Crossrail's eastern tunnels will run for 8.3km (5.16 miles) from Docklands to Farringdon where they will join with the western tunnels from Paddington. When complete, Crossrail will transform rail transport in east London with areas such as Whitechapel, Ilford and Romford gaining direct links to the capital’s major employment areas.

Ahead of tunnelling, Crossrail has been working hard to limit the impact on local communities. Construction of a new jetty began this week at Instone Wharf and will enable excavated material to be transported by ship rather than road, removing 30,000 lorries from east London roads. Around 1.2 million tonnes of excavated material will be transported by boat.

Construction of a 100 x 9 metre muck pit has also begun this week. The pit will store excavated material when the tide is too low or there is no ship at the jetty.

Crossrail's Eastern Tunnels Project Manager Peter Main said: "We are now gearing up for the start of Crossrail tunnelling in east London. Work to construct two large launch shafts is now complete with assembly of the first of our tunnel boring machines now well underway. We understand how critical it is to limit the impact of Crossrail's construction on local communities and have planned to transport the excavated material from the eastern tunnels by boat from Instone Wharf, removing the need for more than 30,000 lorry journeys in east London. We will also deliver 120,000 concrete tunnel segments by boat from Chatham Dockyard to further reduce our local impact."

(CD)

Latest Construction News

17/05/2024

Birmingham City Council has approved plans to develop over 1,300 new homes and 2,700 square metres of commercial space, at Warners Fields. The plans were submitted by Dandara Living. Work can now begin to regenerate the brownfield site, which is located within a mile of the city centre in ...
17/05/2024

United Living Property Services (ULPS) has scooped a 14-year contract with L&Q as part of its sector-leading Major Works Investment Programme. The contract, worth up to £205 million, covers all planned investment and regeneration works across L&Q homes in Trafford and forms part of the housing ...
17/05/2024

Network Rail, Tees Valley Combined Authority, and Stockton-on-Tees Borough Council have commenced work to transform Eaglescliffe railway station and make it more accessible for passengers. A multi-million-pound project will see accessibility at the station improved with the installation of a new ...
17/05/2024

South Kesteven District Council (SKDC) has secured an additional £3,587,500 for energy efficiency upgrades at The Meres Leisure Centre. The award, from the Public Sector Decarbonisation Scheme Phase 3c, will pay for a new low-carbon heating system, with an additional £492,500 coming from the ...
17/05/2024

Crash Barriers work by absorbing the forces of an impact with a vehicle and transferring the load to the Crash Barrier. Some systems use a strong, more rigid posts to transfer the load to the posts as well as the horizontal beams so they do not deflect so much under impact. Other types use ...
17/05/2024

You only need to apply to one SSIP accreditation scheme. They all follow the ...
17/05/2024

Treatment of Process Wastewater from a Small Brewery using a Simple Wetland System. Since 2005 Purity Brewing Co, based near Alcester in the West Midlands, has been using a passive wetland system, designed by Cress Water Solutions, to treat the wastewater from their brewing operations. At that ...
17/05/2024

Unveiling the Long-Term Durability of ParaProducts in Alkaline Soils. In the realm of civil engineering and geotechnical solutions, understanding and mitigating the impacts of soil conditions are crucial for the sustainability and success of any project. Highly alkaline soils, with pH levels ...
17/05/2024

Aremco Armco crash barriers are incredibly useful in commercial and industrial settings in the UK for a variety of reasons. Here are the top ten benefits: 1. ...
17/05/2024

Octopus Energy and the UK's first covered bond bank, Perenna, have launched the world's first 'Zero Bills' home mortgage, unlocking sustainable homeownership for many more people across the country. 'Zero Bills' is a cutting-edge smart initiative created by Octopus that allows customers to move ...
JWCAqua Direct LtdLakeside HireBRICOFLOR UKEfco UK LtdThink Construction Skills Ltd.No HydroFour Jays GroupRichman Brick & Stone LtdLuxcrete Limited
Terms and Conditions
2024/05/19 04:21:47