RMD Kwikform pulled out all the stops to win a contract from Bouygues Travaux Publics and Dunne Building & Civil Engineering for the Tyne Tunnel, creating a unique concept for a 21 metre long, 60 tonne falsework traveller system - in just 7 days.
For formwork and falsework specialist RMD Kwikform, given 7 days to go back to the drawing board, following an unsuccessful bid for an important contract on the Tyne Tunnel, led to the conception of the company’s most innovative travelling tunnel soffit support system to date.
Having secured the deal through Concessionaire TT2's main Design and Build Contractor Bouygues Travaux Publics at the final hour, engineers teamed up with North tunnel section subcontractor, Dunne Building & Civil Engineering, combining expertise to successfully utilise the unique traveller system.
Travelling on the equivalent of train tracks, the RMD Kwikform traveller used a combination of specially designed and standard equipment to create a solid yet flexible structure, capable of snaking up an incline of 6%. Withstanding loads of up to 750 tonnes the traveller was capable of supporting up to 300 cubic metres of concrete poured over 173 square metres.
The 21m long traveller system was used by Dunne Civil Engineering to successfully cast the nine, 1200mm thick roof slabs that make up the roof of the tunnel’s North section for the Tyne Tunnel operator, TT2 who, together with Project Promoter the Tyne and Wear Integrated Transport Authority (TWITA), funded £260m project.
For RMD Kwikform Engineering Director, Ian Fryer who led the four strong engineering design team for the project, overcoming the challenges faced at both the design and utilisation stages of the project were particularly rewarding.
Ian said: "When you are challenged to go back to the drawing board on a project of this scale and importance, it tests all of your engineering knowledge and capabilities.
"The challenge was to deliver a whole-slab-area travelling formwork system with 2 metre height variation which could be operated without the site staff working at height. The traveller also needed to give the users the flexibility to snake the equipment up an incline of 6%, travelling on rails whilst casting a slab that was up to 8.5 metres off the ground, at the bottom of a 25 metre deep excavation full of large ground shoring props.
"Once we had overcome the design element and been awarded the contract by Bouygues Travaux Publics, we entered the phase of taking the proposal design to the end solution. At this time, because the works for the North contract were subcontracted to Dunne Civil Engineering, we had to deal with a new construction team to demonstrate how the system would work.
"At this stage Dunne's were able to assist the design team with suggested amends to the design in order for the system to best meet the needs of the site team. The very tight programme schedule also placed further challenges on the delivery and erection of equipment, which physically required assembling and commissioning 60 tonnes of system and special components at the base of what is effectively a large hole.
"As part of the intensive design and detailing phase that followed, the first thing the team concentrated on was the calculations, detailing, procurement and fabrication of the special items of equipment needed for the project. Shortly followed by production of the general arrangement drawings required for assembly and the detailed instructions for use of the machine.
"Procurement of the special equipment, (which included the hydraulic leg components that were central to the function of the traveller), ultimately determined whether the system could be assembled and operated within the time frame required."
Having developed an assembly sequence in collaboration with Dunne’s for the traveller, RMD Kwikform provided three customer service team members to assist with the erection of the traveller which as a part of the design required the support legs to always be perpendicular to the slope of the soffit.
Unlike previous travellers designed by RMD Kwikform, which incorporated structural steel work at the soffit level, the RMD Kwikform engineering team recognised the opportunity to adapt its R700 truss girder panels for use on this project. By adapting the R700 girders with specially fabricated cantilever frames at the ends, the units were used to span across the tunnel whilst still maintaining sufficient headroom beneath to accommodate site traffic, such as concrete mixers and scissor lifts.
Having to negotiate both varying horizontal and vertical curves, the 21 metre long traveller had to be flexible enough to be able to be travelled around the tunnel profile, rising from its start point at the river side end wall. For this reason RMD Kwikform split the structure into three 7.2m long rectangular tables, which were linked by adjustable bays of equipment that could be changed in length to adjust the horizontal and vertical curvature of the entire assembly and provided sufficient flexibility during travelling to accommodate level tolerances in the running rails.
Advancing up to 21 metres in about an hour, the RMD Kwikform traveller system has reduced the time for slab pouring significantly when compared with traditional methods. This in-turn allowed this section of the project to be completed on-schedule by the end of November 2009.
For further information contact RMD Kwikform on Tel: 01922 743743 or Email: info@rmdkwikform.com
Construction News
09/03/2010
RMD Kwikform's Unique Tyne Tunnel Traveller System


02/07/2025
Construction is officially underway on the new Whitefield Community Fire Station, part of Greater Manchester Fire and Rescue Service's (GMFRS) £38 million Estates Improvement Programme.
Led by Robertson Construction North West, the project will replace the former fire station on Bury New Road with

02/07/2025
Hull City Council has officially appointed Esh Construction to lead a major repair and strengthening programme on Drypool Bridge, one of the city's key transport links.
The project will be delivered in partnership with engineering consultancy Mason Clark Associates.
Work will begin on the south s

02/07/2025
Award-winning housebuilder The Hill Group has announced record financial results for the year ending 31 March 2025, marking its second consecutive year of historic growth.
The company reported a turnover of £1.15 billion and a pre-tax profit of £90.5 million, completing more than 2,800 new homes a

02/07/2025
Women in Construction Anglia (WICA) and Suffolk Chamber of Commerce have voiced strong support for the government's new plans to increase the construction workforce by 100,000 people annually.
The announcement follows the launch of the first Construction Skills Mission Board, attended by Work and P

02/07/2025
Huddersfield Station will undergo a significant upgrade this autumn as part of the multi-billion-pound Transpennine Route Upgrade (TRU), with a full 30-day closure scheduled from Saturday 30 August to Sunday 28 September 2025.
The closure represents a major milestone in the delivery of a faster, gr

02/07/2025
Procurement Hub, part of Places for People (PfP), has confirmed a two-year extension of its flagship Major Projects Framework 2 (MPF2), extending its term until 2028 after achieving more than £300 million in social value since its launch in 2022.
Designed to deliver a more efficient, equitable, and

02/07/2025
Two Galliford Try employees have received commendations at this year's British Ex-Forces in Business Awards, recognising their outstanding contributions and leadership within the construction industry after transitioning from military service.
Pam McNeill, Business Assurance Manager for Galliford T

02/07/2025
The government has announced a landmark £39 billion investment to deliver around 300,000 new social and affordable homes across the UK over the next decade, in a major bid to tackle the housing crisis and provide secure housing for families and children stuck in temporary accommodation.
Under the n

02/07/2025
Hydrogen sulfide (H₂S) is one of the most dangerous gases found in industrial environments.
Colourless, highly toxic, and often referred to as the "silent killer", it's particularly hazardous because it can quickly deaden the sense of smell, giving workers a false sense of security.
Even a

02/07/2025
The Federation of Master Builders (FMB) has welcomed the Construction Leadership Council's (CLC) new Health, Safety and Wellbeing Strategy, describing it as a much-needed step toward driving change across the construction industry.
FMB Chief Executive Brian Berry joined over 140 industry leaders at