Results from a new piece of research by the Chartered Institute of Building (CIOB) has revealed that a high proportion of complex construction projects are likely to be finished more than six months late, due to poor time control.
The CIOB's research was completed by more than 70 respondents in the UK and provided data on over 2000 projects. The research examined the construction industry’s methods to manage time on projects, in particular the techniques used and the competence of those engaged in the process.
Keith Pickavance CIOB Senior Vice President commented: "In the last ten years we have seen massive developments in hardware, software and communications that have made it virtually impossible to efficiently conduct any business without the use of computers and electronic services. The construction industry uses those facilities intensively in many areas including, design, manufacture, procurement, assembly and finance. In fact it uses them in virtually every field other than time-management, which currently does not use the available technology effectively.
"The growth in training, education and skill levels within the industry in the use of time-management techniques has not kept pace with the technology available. This should be of concern to many companies, as there is a trend towards developing contracts which are increasingly punitive if not executed efficiently.
"It should be recognised that the industry manages many projects very well indeed and the UK construction industry in particular is regarded around the world as a leading force; but we have to accept that respondents in this survey regarded the quality of time-management on construction projects as generally poor. Over half were familiar with only a master schedule being used, with no short term planning. Such schedules would typically be in bar chart form with no linked sequencing. In their experience, managers consequently would be unable to measure the impact slippage or the imposed changes on the works. Therefore managers would not be able to manage the effects of the delay on project completion, except intuitively."
According to the respondents certain types of project have a reasonable chance of being finished by, or before the completion date, using traditional methods of time-management and without modern methods of time control. These include, low-rise offices, and commercial, industrial, housing, schools and educational buildings, shops and shopping malls.
However, the results also show that more complex projects have a poor chance of being completed on time without advanced methods of project control being employed. These include hospital, clinic and health-related buildings, prisons and security infrastructure, stadia, railway and high-rise projects.
(JM/CD)
Construction News
20/06/2008
Contractors Held To Blame For Construction Delays
.gif)

04/07/2025
JV North has announced the list of contractors and consultants appointed to its £500 million social housebuilding framework, which aims to deliver around 3,000 homes across the North West over the next four years.
The housing consortium, which includes 14 members, launched the procurement process i

04/07/2025
Work has officially started on preparing Eston Precinct for demolition, marking the first step in a major regeneration project led by Redcar & Cleveland Borough Council.
Esh Construction has been appointed to deliver the scheme, which will begin with the safe removal of asbestos and the soft strip

04/07/2025
The Secretary of State for Energy Security and Net Zero hasgranted development consent for the Mona Offshore Wind Farm.
The scheme, located in the Irish Sea, will deliver approximately 1,500MW of clean energy capacity and forms part of the Round 4 Offshore Wind Licensing Arrangements. The applicati

04/07/2025
The restoration of Chatham’s iconic Brook Theatre is officially underway, with the appointment of contractors to carry out the £21 million transformation of the 125-year-old building.
Originally opened in 1899 as Chatham Town Hall, the Grade II listed Renaissance-style landmark has served the commu

04/07/2025
Work to upgrade a flood-prone section of Stockbridge Road in Timsbury is set to begin later this month, as part of a joint project between the Environment Agency and Hampshire County Council to improve local flood defences.
Starting on 28 July, the five-week scheme will deliver vital improvements a

04/07/2025
Oldham's town centre regeneration has taken a major step forward, with planning consent now granted for all six sites earmarked for transformation through the partnership between Muse and Oldham Council.
The approval represents a significant milestone in the long-term vision to create a vibrant, in

04/07/2025
As temperatures soared during this week's heatwave, euroloo's innovative EcoWelfare units proved to be a game-changer on construction and outdoor sites across the country.
Designed with comfort and sustainability in mind, these multi-functional welfare units offer everything teams need to stay pro

04/07/2025
Atlas Site Engineering, a trusted name in precision setting out and site engineering services, continues to support the construction industry with expert solutions ranging from small residential extensions to multi-storey high-rise developments.
With a reputation for accuracy and reliability, Atlas

03/07/2025
Associated British Ports (ABP) has submitted a reserved matters application for 103,000 sq ft of speculative industrial and logistics space at Helm @ Immingham.
This marks the first phase of development at the 227-acre site.
The scheme will deliver a range of purpose-built units from 4,820 sq ft

03/07/2025
First Choice Homes Oldham (FCHO) is set to begin a major new phase of energy efficiency upgrades this month, with a £6.1 million investment aimed at improving 645 homes across the borough.
Starting 14 July, properties in Abbey Hills, Roundthorn, Shaw, and several estates in Chadderton will receive