Results from a new piece of research by the Chartered Institute of Building (CIOB) has revealed that a high proportion of complex construction projects are likely to be finished more than six months late, due to poor time control.
The CIOB's research was completed by more than 70 respondents in the UK and provided data on over 2000 projects. The research examined the construction industry’s methods to manage time on projects, in particular the techniques used and the competence of those engaged in the process.
Keith Pickavance CIOB Senior Vice President commented: "In the last ten years we have seen massive developments in hardware, software and communications that have made it virtually impossible to efficiently conduct any business without the use of computers and electronic services. The construction industry uses those facilities intensively in many areas including, design, manufacture, procurement, assembly and finance. In fact it uses them in virtually every field other than time-management, which currently does not use the available technology effectively.
"The growth in training, education and skill levels within the industry in the use of time-management techniques has not kept pace with the technology available. This should be of concern to many companies, as there is a trend towards developing contracts which are increasingly punitive if not executed efficiently.
"It should be recognised that the industry manages many projects very well indeed and the UK construction industry in particular is regarded around the world as a leading force; but we have to accept that respondents in this survey regarded the quality of time-management on construction projects as generally poor. Over half were familiar with only a master schedule being used, with no short term planning. Such schedules would typically be in bar chart form with no linked sequencing. In their experience, managers consequently would be unable to measure the impact slippage or the imposed changes on the works. Therefore managers would not be able to manage the effects of the delay on project completion, except intuitively."
According to the respondents certain types of project have a reasonable chance of being finished by, or before the completion date, using traditional methods of time-management and without modern methods of time control. These include, low-rise offices, and commercial, industrial, housing, schools and educational buildings, shops and shopping malls.
However, the results also show that more complex projects have a poor chance of being completed on time without advanced methods of project control being employed. These include hospital, clinic and health-related buildings, prisons and security infrastructure, stadia, railway and high-rise projects.
(JM/CD)
Construction News
20/06/2008
Contractors Held To Blame For Construction Delays
.gif)

06/05/2025
Scarborough Group International (SGI) has announced its vision for the next phase of development at Thorpe Park Leeds, outlining plans to introduce a major industrial and logistics hub, new urban apartments, and additional Grade A business spaces with supporting amenities.
Building on more than 25

06/05/2025
Kirklees Council has submitted updated plans for the refurbishment of the historic George Hotel in Huddersfield, proposing an increase in guest rooms while carefully preserving the landmark building's architectural and heritage features.
Working in partnership with architects and Historic England,

06/05/2025
Persimmon Homes has officially broken ground on its new Hawthorn Park development in Leominster, welcoming local councillors to the site to mark the start of construction.
The Deputy Leader of Herefordshire Council, Councillor Elissa Swinglehurst, and Councillor Allan Williams, who represents Leomi

06/05/2025
Engineering and infrastructure group Murphy has announced a strategic partnership with Australia-based Abergeldie Complex Infrastructure.
The deal will see Murphy take a 40% stake in Abergeldie, a move that strengthens both companies' capabilities and reflects a shared commitment to values-led infr

06/05/2025
Network Rail has completed a programme of emergency repairs to an embankment on the Brighton Main Line near Three Bridges, restoring full safety and stability to a key stretch of one of the country's busiest rail routes.
The repairs were carried out after a landslip occurred between Three Bridges a

06/05/2025
As the UK's new Online Safety Act brings strict protections for young people online, training provider Essential Site Skills latest blog highlights the wider impact these measures will have on safeguarding the workforce of tomorrow.
Click

06/05/2025
We decided to group these subjects into one page as they're all closely related. This information was updated in July 2019 and is accurate at time of writing.
Grade 1 Lowest
Intruders are expected to have little knowledge of the alarm system and may be restricted to a limited range of tool

06/05/2025
Looking for a standing stairlift in the UK? Read on...
Which manufacturers make stand-up stairlifts, who needs them, their benefits, and how much do they cost? Let's discover compact stand-on stair lifts for the elderly, people with joint problems or those with staircases too narrow to fit a tradit

06/05/2025
With over 1.4 million kilometres of underground services in the UK, underground cables, pipes, and services are hit and damaged every day, sometimes resulting in serious injury, the cost of repair, and a loss of business reputation.
This is mainly caused by operatives not being able to use cable av

06/05/2025
The max weight limit for a straight stairlift is 31 stone, or 197kg, however there's much more choice at 25 stone weight limit.
For curved stairlifts the max weight limit is 30 stone, or 190kg, however there's much more choice at 19 stone limit.
Overweight people with mobility issues can face esp