Construction News

27/03/2023

HS2 Establishes Rebar Threading Facility

Construction News Image

HS2 has established a rebar threading facility to address materials shortages at its Copthall tunnel construction site in Hillingdon - creating jobs, cutting waste and reducing lorry movements.

The new facility will make 92,000 rebar couplers, needed to construct the Copthall tunnel.

The Skanska Costain STRABAG joint venture (SCS JV) team constructing the tunnel were faced with delays due to a shortfall of available prefabricated fatigue rated rebar couplers, after suppliers had exited the market. To address this, the team has constructed a threading facility on site to produce the required quantities of the materials themselves.

As well as addressing supply shortfall, the threading facility has resulted in a significant financial saving on the project by reducing waste, costs and lorry movements, and overall creating a more efficient way of working.

-- Advertisement --
hss

To construct the 880 metre long cut and cover Copthall tunnel, 92,000 fatigue rated couplers are required. A team of 14 will work at the facility six days a week, 8 hours a day for three years to meet the supply needs for the tunnel.

The process to get the facility up and running took 20 weeks in total, with the team gaining CARES certification (assured certification for the constructional steels industry) for the work and securing the required equipment from Sheffield based company, Leviat. It is only the second time CARES certification has been given for this activity to happen onsite.

The team purchase stock rebar and then complete processing operations on site, before taking it through the four-step threading process and delivering it to the Copthall tunnel construction area. All the work is taking place within the site boundary reducing unnecessary lorry movements, supporting HS2 Net Zero Carbon targets.

The solution was devised by Ray Moloney, Senior Project Manager for SCS JV, who explains his approach: "Uncertainties in the market and the need to meet the requirements of the HS2 construction programme meant that we had to look at an innovative solution for supplying fatigue rated mechanical reinforcement connections. In mid-2022 we started engaging with partners including Leviat and CARES to develop an on-site processing scheme and within 20 weeks, we were processing our first order.

"The solution has created new jobs, offered new training opportunities for engineers and means that we can remove the risk of any delays in construction due to supply shortages."

Latest Construction News

10/06/2026
Mitie has expanded its partnership with the Government Property Agency (GPA), landing a £4 million, three-year facilities management contract to support refurbished offices in Peterborough and Whitehall. The deal spans three sites: Quay House, the flagship regional hub in Peterborough, and two Grade
Read More
10/06/2026
Network Rail's £23m, world-first overhead line system has been installed during a 16‑day closure to combat corrosion in the Severn Tunnel, with extra drainage, track and station works delivered around Bristol. Train services have resumed through the Severn Tunnel after Network Rail finished a
Read More
10/06/2026
NASC Safety Report 2026 shows historically low accident rates even as membership surges, while wider construction industry records 35 fatal falls from height National Access & Scaffolding Confederation (NASC) members recorded zero operative fatalities in 2025, according to the 2026 NASC Safety Repo
Read More
10/06/2026
Ofgem has awarded almost £500,000 from its Strategic Innovation Fund, delivered in partnership with Innovate UK, to SSEN Distribution's FORTRESS project, enabling the hospital decarbonisation scheme to advance to the Alpha development phase. FORTRESS — short for flexibility and optimisation for res
Read More
10/06/2026
Bradford District Care NHS Foundation Trust has officially broken ground on the second phase of its £65 million redevelopment project at Lynfield Mount Hospital. The major milestone follows final approval from the Department of Health and Social Care in January 2026 to push forward with the extensi
Read More
10/06/2026
Hampshire-based housebuilder Pennyfarthing Homes has submitted a detailed reserved matters planning application for the next phase of its Sandle Park development in Fordingbridge. Situated off Whitsbury Road, this latest proposal follows the approval of the project's initial 74-home phase in May 202
Read More
10/06/2026
International property and construction consultancy Gleeds has been chosen as the lead consultant tasked with developing the Regeneration Framework for the Trent Sports District. The major project is set to serve as a significant driver of economic growth for Nottingham and the wider East Midlands r
Read More
10/06/2026
FIS has launched a new e-learning module, Building Regulation Compliance: Contractor Roles (linked below), designed to help construction professionals understand and meet their responsibilities under the latest regulatory changes. The new competency-led e-learning module provides clear, practical g
Read More
09/06/2026
Costain, the infrastructure solutions company, has been selected by Transport for London (TfL) to join its Infrastructure Improvement Framework. The multi-discipline framework, covering both design and construction, will allow for major infrastructure upgrades across the capital. This includes upgr
Read More
09/06/2026
Work on the new Kirk Hill bridge at Sutton Bonington is advancing well, with 14,000 bricks now installed in the new parapet walls on the structure. The scheme will create the clearance needed for larger‑gauge freight trains, enabling more goods to move by rail, and improve maintenance access
Read More
Pro Structures LtdBRICOFLOR UKLakeside HireClassical CreationsCress Water Solutions LtdShaw SecurityStairlift Solutions NI, NewtownardsMaterials Movement LtdHowdens Joinery LarneSoluform