Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 146,394 companies....

Construction News

31/07/2012

CDM, Paperwork & Competence

Why all the paper?

As a practising health and safety professional and CDM co-ordinator it continues to confound Callsafe Services Limited as to organisations’ and construction projects’ preoccupation with paperwork and the desire to preclude any liabilities.

Callsafe Services Limited has been providing advice, assistance and training to our clients, and our clients’ projects, for nearly 25 years. Our clients have included many central and local government organisations, as well as private industry clients, designers and contractors.

The following article expresses the concerns of Callsafe Services Limited with the application of the Construction (Design and Management) Regulations 2007 (CDM), its Approved Code of Practice, L144, Managing health and safety in construction, and what could be considered to be best practice, with, where possible, suggested improvements to the way construction project health and safety is managed. We concur with the findings of Professor Ragnar Löfstedt, and presented in his report, that the CDM regulations are generally useful and proportionate, but that the application of the regulations on projects are not universally either useful or proportionate. The author’s words, rather than Professor Löfstedt’s.

Our first concern is the method of competence assessment still applied within the industry, based on the requirements L144, Appendix 4. If the elements of Appendix 4 are all questioned and answered as part of a particular project’s procurement, the effort and paper required to achieve this is extraordinary. It is accepted that competence is an essential element of effective health and safety management, but why are many organisations still preferring to utilise their specifically developed assessment systems rather than using industry accreditations, as exemplified by ‘Safety Schemes in Procurement’ (SSIP)?. SSIP only addresses stage 1 of the Appendix 4 competence assessment, but this is the most difficult part of the assessment with regards to effort, cost and paper. If SSIP accreditation is accepted by the majority of procuring organisations we will all be able to concentrate on the specific project issues, such as the competence of proposed personnel to the project and the resources allocated.

-- Advertisement --
hss

The continuing reliance on documents is demonstrated clearly by the methods used to disseminate the pre-construction information (PCI). Most projects still produce the PCI as a document to accompany the contractors’ tender documents. It is the author’s belief that this does not comply with the PCI requirements of CDM. This is because the PCI is not only required to inform the contractors, it is also required to inform the designers and design.

This lack of focus on what is necessary was demonstrated on a ‘design & build’ project for which Callsafe Services Limited was appointed as CDM co-ordinator. The principal contractor had been involved in the project planning and design from commencement of detailed design, but still requested a PCI document prior to him producing the construction phase plan (CPP). The principal contractor, after some discussion, agreed that he did not need a PCI document, as he already had in his possession all of the information. If tenders are being prepared, a PCI document still makes sense, but if the project delivery team are all in place at an early stage in the project, e.g. with early contractor involvement (ECI), a document/information register, with distributions, would make more sense and would actually be useful.

It is also unfortunate that many of these PCI documents contain much ‘generic’ information, and not enough project/site-specific information. Many of these documents contain many pages, sometimes plus 100 pages, which makes it very difficult to extract the important information from that which is already known by competent designers and contractors.

The Approved Code of Practice, L144, is not clear as to the uses of the PCI, as it states in paragraphs 55 and 56 that the PCI must be provided to designers and contractors who may be bidding for the work (or who they intend to engage). If an amendment to the Approved Code of Practice is to be made, this could usefully be clarified to include ‘all designers and contractors tendering for the work or working on the project’.

Designers are producing many and varied ‘design risk assessments’, ‘design risk registers’, ‘design hazard inventories’, and many other varieties of paper evidence of their compliance with the designers’ duties under CDM. The question has to be asked as to why they are doing this? The regulations do not require these documents to be produced, only that the designers should supply information to any person affected about the design, the significant residual risks, the designers’ assumptions and any difficulties associated with materials specified, subsequent to attempting, so far as reasonably practicable, to eliminate and reduce risks by their design decisions. Most of this documentation is produced to be able to demonstrate to anyone criticising the design or attempting to prosecute or sue the designer that they have considered the risks. This is understandable, and the documents can be useful when performing design co-ordination and design review, although it is suggested that they could be simplified and made more useful. The other questions relating to the designers’ duties are why so many aspects of the design are incorporated just because they had been used before; and the extent to which designers have to inform competent contractors of significant risks remaining? Do we really need to inform the competent contractor that falling 5 metres is likely to cause harm?

It is incumbent on ALL designers to co-operate with, and co-ordinate their designs with, other designers. This not only applies between the permanent works designers, but includes temporary works designers. Client procurement arrangements must allow this design co-operation and co-ordination to take place, e.g. where there is a design interface the designers of that interface need to be working on the project at the same time, or at least with an overlap.

David Carr, PgD, FIIRSM, DipSM, RFaPS, Registered Consultant

Callsafe Services Limited, Yardley House, 11 Horsefair, Rugeley, Staffordshire. WS15 2EJ

[email protected]

www.callsafe-servcies.co.uk

Latest Construction News

17/07/2026
Jacobs has secured three new commissions with National Highways, strengthening its role in supporting the modernization, resilience and long-term performance of the UK’s strategic road network. The appointments will see Jacobs deliver key asset renewal and project leadership services designed to im
Read More
17/07/2026
Vistry and Platform Housing Group have joined forces to deliver a 177-home, 100% affordable housing development on the former Simon Digby School site in Chelmsley Wood, Solihull. The 4.5-hectare site, which has been identified for residential development for more than a decade, will see Platform Ho
Read More
17/07/2026
A new housing development in Devizes is set to deliver more than £3.5 million in funding for local services and infrastructure, as the first homes are completed at the site. Bellway's Lock Keeper Gardens development, located on land between Coate Road and the Kennet and Avon Canal on the eastern ed
Read More
17/07/2026
Morgan Sindall Construction has been reappointed to both value bands of the new £1.5bn YORbuild Major Works 2 framework, which will deliver major public-sector building projects across Yorkshire and the Humber and adjacent areas. The renewed places extend the company's long-standing partnership wit
Read More
17/07/2026
As the UK construction industry continues to demonstrate resilience amid ongoing economic uncertainty, experts within the invoice finance sector are reporting increased demand from construction businesses seeking flexible working capital solutions to support growth, manage rising costs, and overcome
Read More
17/07/2026
Preparatory works have commenced in West Vale on a transport improvement programme designed to better link Elland town centre with neighbouring areas. Approved by planners in November 2024, the package aims to deliver safer, more convenient routes and to enhance access to the planned new Elland Rai
Read More
17/07/2026
Sefton Council's cabinet will next week be asked to approve the next stage of its Sefton 2030 housing programme, enabling partner The Sovini Group to start feasibility work on three potential development sites: the former Ainsdale Hope School, the Professional Development Centre in Formby, and the f
Read More
17/07/2026
The Mayor of Olney, Councillor Debbie Whitworth, has officially opened a new community facility at Yardley Manor, a mixed-tenure residential development being delivered by Vistry and Taylor Wimpey in Buckinghamshire. The new building has been created as a central meeting place for residents and loc
Read More
17/07/2026
Yorkshire Water has begun work to upgrade equipment at the Ecclesall Road and Granville Road combined storm overflows (CSOs) in Sheffield. The works involve installing new mechanical screens, kiosks and control panels, alongside upgrades to mechanical and engineering instrumentation, to improve the
Read More
17/07/2026
Knowsley Council's Cabinet has agreed to move forward with the next stage of investment in Kirkby town centre, approving plans for a leisure-led scheme at the heart of the town. The Council has already committed more than £43.8 million to Kirkby since purchasing the town centre from the private sec
Read More
Lakeside HireBRICOFLOR UKPro Structures LtdPace ConsultAxis Entrance Systems LtdKirby and Wells Ltd -  Kawstore  (CompanyID 491878 / CopyId 228904)Ceildoor Products LimitedMezzanine Floor Engineering LtdMayfair Steel BuildingsAllcott Commercial