Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
31/07/2012

CDM, Paperwork & Competence

Why all the paper?

As a practising health and safety professional and CDM co-ordinator it continues to confound Callsafe Services Limited as to organisations’ and construction projects’ preoccupation with paperwork and the desire to preclude any liabilities.


Callsafe Services Limited has been providing advice, assistance and training to our clients, and our clients’ projects, for nearly 25 years. Our clients have included many central and local government organisations, as well as private industry clients, designers and contractors.

The following article expresses the concerns of Callsafe Services Limited with the application of the Construction (Design and Management) Regulations 2007 (CDM), its Approved Code of Practice, L144, Managing health and safety in construction, and what could be considered to be best practice, with, where possible, suggested improvements to the way construction project health and safety is managed. We concur with the findings of Professor Ragnar Löfstedt, and presented in his report, that the CDM regulations are generally useful and proportionate, but that the application of the regulations on projects are not universally either useful or proportionate. The author’s words, rather than Professor Löfstedt’s.

Our first concern is the method of competence assessment still applied within the industry, based on the requirements L144, Appendix 4. If the elements of Appendix 4 are all questioned and answered as part of a particular project’s procurement, the effort and paper required to achieve this is extraordinary. It is accepted that competence is an essential element of effective health and safety management, but why are many organisations still preferring to utilise their specifically developed assessment systems rather than using industry accreditations, as exemplified by ‘Safety Schemes in Procurement’ (SSIP)?. SSIP only addresses stage 1 of the Appendix 4 competence assessment, but this is the most difficult part of the assessment with regards to effort, cost and paper. If SSIP accreditation is accepted by the majority of procuring organisations we will all be able to concentrate on the specific project issues, such as the competence of proposed personnel to the project and the resources allocated.

-- Advertisement --
hss

The continuing reliance on documents is demonstrated clearly by the methods used to disseminate the pre-construction information (PCI). Most projects still produce the PCI as a document to accompany the contractors’ tender documents. It is the author’s belief that this does not comply with the PCI requirements of CDM. This is because the PCI is not only required to inform the contractors, it is also required to inform the designers and design.

This lack of focus on what is necessary was demonstrated on a ‘design & build’ project for which Callsafe Services Limited was appointed as CDM co-ordinator. The principal contractor had been involved in the project planning and design from commencement of detailed design, but still requested a PCI document prior to him producing the construction phase plan (CPP). The principal contractor, after some discussion, agreed that he did not need a PCI document, as he already had in his possession all of the information. If tenders are being prepared, a PCI document still makes sense, but if the project delivery team are all in place at an early stage in the project, e.g. with early contractor involvement (ECI), a document/information register, with distributions, would make more sense and would actually be useful.

It is also unfortunate that many of these PCI documents contain much ‘generic’ information, and not enough project/site-specific information. Many of these documents contain many pages, sometimes plus 100 pages, which makes it very difficult to extract the important information from that which is already known by competent designers and contractors.

The Approved Code of Practice, L144, is not clear as to the uses of the PCI, as it states in paragraphs 55 and 56 that the PCI must be provided to designers and contractors who may be bidding for the work (or who they intend to engage). If an amendment to the Approved Code of Practice is to be made, this could usefully be clarified to include ‘all designers and contractors tendering for the work or working on the project’.

Designers are producing many and varied ‘design risk assessments’, ‘design risk registers’, ‘design hazard inventories’, and many other varieties of paper evidence of their compliance with the designers’ duties under CDM. The question has to be asked as to why they are doing this? The regulations do not require these documents to be produced, only that the designers should supply information to any person affected about the design, the significant residual risks, the designers’ assumptions and any difficulties associated with materials specified, subsequent to attempting, so far as reasonably practicable, to eliminate and reduce risks by their design decisions. Most of this documentation is produced to be able to demonstrate to anyone criticising the design or attempting to prosecute or sue the designer that they have considered the risks. This is understandable, and the documents can be useful when performing design co-ordination and design review, although it is suggested that they could be simplified and made more useful. The other questions relating to the designers’ duties are why so many aspects of the design are incorporated just because they had been used before; and the extent to which designers have to inform competent contractors of significant risks remaining? Do we really need to inform the competent contractor that falling 5 metres is likely to cause harm?

It is incumbent on ALL designers to co-operate with, and co-ordinate their designs with, other designers. This not only applies between the permanent works designers, but includes temporary works designers. Client procurement arrangements must allow this design co-operation and co-ordination to take place, e.g. where there is a design interface the designers of that interface need to be working on the project at the same time, or at least with an overlap.

David Carr, PgD, FIIRSM, DipSM, RFaPS, Registered Consultant

Callsafe Services Limited, Yardley House, 11 Horsefair, Rugeley, Staffordshire. WS15 2EJ

enquiries@callsafe-services.co.uk

www.callsafe-servcies.co.uk

Latest Construction News

17/05/2024

Birmingham City Council has approved plans to develop over 1,300 new homes and 2,700 square metres of commercial space, at Warners Fields. The plans were submitted by Dandara Living. Work can now begin to regenerate the brownfield site, which is located within a mile of the city centre in ...
17/05/2024

United Living Property Services (ULPS) has scooped a 14-year contract with L&Q as part of its sector-leading Major Works Investment Programme. The contract, worth up to £205 million, covers all planned investment and regeneration works across L&Q homes in Trafford and forms part of the housing ...
17/05/2024

Network Rail, Tees Valley Combined Authority, and Stockton-on-Tees Borough Council have commenced work to transform Eaglescliffe railway station and make it more accessible for passengers. A multi-million-pound project will see accessibility at the station improved with the installation of a new ...
17/05/2024

South Kesteven District Council (SKDC) has secured an additional £3,587,500 for energy efficiency upgrades at The Meres Leisure Centre. The award, from the Public Sector Decarbonisation Scheme Phase 3c, will pay for a new low-carbon heating system, with an additional £492,500 coming from the ...
17/05/2024

Crash Barriers work by absorbing the forces of an impact with a vehicle and transferring the load to the Crash Barrier. Some systems use a strong, more rigid posts to transfer the load to the posts as well as the horizontal beams so they do not deflect so much under impact. Other types use ...
17/05/2024

You only need to apply to one SSIP accreditation scheme. They all follow the ...
17/05/2024

Treatment of Process Wastewater from a Small Brewery using a Simple Wetland System. Since 2005 Purity Brewing Co, based near Alcester in the West Midlands, has been using a passive wetland system, designed by Cress Water Solutions, to treat the wastewater from their brewing operations. At that ...
17/05/2024

Unveiling the Long-Term Durability of ParaProducts in Alkaline Soils. In the realm of civil engineering and geotechnical solutions, understanding and mitigating the impacts of soil conditions are crucial for the sustainability and success of any project. Highly alkaline soils, with pH levels ...
17/05/2024

Aremco Armco crash barriers are incredibly useful in commercial and industrial settings in the UK for a variety of reasons. Here are the top ten benefits: 1. ...
17/05/2024

Octopus Energy and the UK's first covered bond bank, Perenna, have launched the world's first 'Zero Bills' home mortgage, unlocking sustainable homeownership for many more people across the country. 'Zero Bills' is a cutting-edge smart initiative created by Octopus that allows customers to move ...
Lakeside HireThink Construction Skills Ltd.JWCAqua Direct LtdEfco UK LtdBRICOFLOR UKAdvanced Chemical Specialties Ltd.Landscaping CambridgeSolibri UK LtdMy Thread Curtains
Terms and Conditions
2024/05/19 02:08:59