Why all the paper?
As a practising health and safety professional and CDM co-ordinator it continues to confound Callsafe Services Limited as to organisations’ and construction projects’ preoccupation with paperwork and the desire to preclude any liabilities.
Callsafe Services Limited has been providing advice, assistance and training to our clients, and our clients’ projects, for nearly 25 years. Our clients have included many central and local government organisations, as well as private industry clients, designers and contractors.
The following article expresses the concerns of Callsafe Services Limited with the application of the Construction (Design and Management) Regulations 2007 (CDM), its Approved Code of Practice, L144, Managing health and safety in construction, and what could be considered to be best practice, with, where possible, suggested improvements to the way construction project health and safety is managed. We concur with the findings of Professor Ragnar Löfstedt, and presented in his report, that the CDM regulations are generally useful and proportionate, but that the application of the regulations on projects are not universally either useful or proportionate. The author’s words, rather than Professor Löfstedt’s.
Our first concern is the method of competence assessment still applied within the industry, based on the requirements L144, Appendix 4. If the elements of Appendix 4 are all questioned and answered as part of a particular project’s procurement, the effort and paper required to achieve this is extraordinary. It is accepted that competence is an essential element of effective health and safety management, but why are many organisations still preferring to utilise their specifically developed assessment systems rather than using industry accreditations, as exemplified by ‘Safety Schemes in Procurement’ (SSIP)?. SSIP only addresses stage 1 of the Appendix 4 competence assessment, but this is the most difficult part of the assessment with regards to effort, cost and paper. If SSIP accreditation is accepted by the majority of procuring organisations we will all be able to concentrate on the specific project issues, such as the competence of proposed personnel to the project and the resources allocated.
The continuing reliance on documents is demonstrated clearly by the methods used to disseminate the pre-construction information (PCI). Most projects still produce the PCI as a document to accompany the contractors’ tender documents. It is the author’s belief that this does not comply with the PCI requirements of CDM. This is because the PCI is not only required to inform the contractors, it is also required to inform the designers and design.
This lack of focus on what is necessary was demonstrated on a ‘design & build’ project for which Callsafe Services Limited was appointed as CDM co-ordinator. The principal contractor had been involved in the project planning and design from commencement of detailed design, but still requested a PCI document prior to him producing the construction phase plan (CPP). The principal contractor, after some discussion, agreed that he did not need a PCI document, as he already had in his possession all of the information. If tenders are being prepared, a PCI document still makes sense, but if the project delivery team are all in place at an early stage in the project, e.g. with early contractor involvement (ECI), a document/information register, with distributions, would make more sense and would actually be useful.
It is also unfortunate that many of these PCI documents contain much ‘generic’ information, and not enough project/site-specific information. Many of these documents contain many pages, sometimes plus 100 pages, which makes it very difficult to extract the important information from that which is already known by competent designers and contractors.
The Approved Code of Practice, L144, is not clear as to the uses of the PCI, as it states in paragraphs 55 and 56 that the PCI must be provided to designers and contractors who may be bidding for the work (or who they intend to engage). If an amendment to the Approved Code of Practice is to be made, this could usefully be clarified to include ‘all designers and contractors tendering for the work or working on the project’.
Designers are producing many and varied ‘design risk assessments’, ‘design risk registers’, ‘design hazard inventories’, and many other varieties of paper evidence of their compliance with the designers’ duties under CDM. The question has to be asked as to why they are doing this? The regulations do not require these documents to be produced, only that the designers should supply information to any person affected about the design, the significant residual risks, the designers’ assumptions and any difficulties associated with materials specified, subsequent to attempting, so far as reasonably practicable, to eliminate and reduce risks by their design decisions. Most of this documentation is produced to be able to demonstrate to anyone criticising the design or attempting to prosecute or sue the designer that they have considered the risks. This is understandable, and the documents can be useful when performing design co-ordination and design review, although it is suggested that they could be simplified and made more useful. The other questions relating to the designers’ duties are why so many aspects of the design are incorporated just because they had been used before; and the extent to which designers have to inform competent contractors of significant risks remaining? Do we really need to inform the competent contractor that falling 5 metres is likely to cause harm?
It is incumbent on ALL designers to co-operate with, and co-ordinate their designs with, other designers. This not only applies between the permanent works designers, but includes temporary works designers. Client procurement arrangements must allow this design co-operation and co-ordination to take place, e.g. where there is a design interface the designers of that interface need to be working on the project at the same time, or at least with an overlap.
David Carr, PgD, FIIRSM, DipSM, RFaPS, Registered Consultant
Callsafe Services Limited, Yardley House, 11 Horsefair, Rugeley, Staffordshire. WS15 2EJ
enquiries@callsafe-services.co.uk
www.callsafe-servcies.co.uk
Construction News
31/07/2012
CDM, Paperwork & Competence

16/05/2025
South Dock Marina in Southwark is set for a major £8 million overhaul aimed at improving health and safety across the site, following the recent approval of a redevelopment plan.
Led by Southwark Council, the upgrade programme has been granted planning permission, pending further consultation with

16/05/2025
The South Rail Systems Alliance (SRSA) has completed a major programme of infrastructure upgrades on the West Anglia main line.
Appointed in September 2023, the SRSA, comprising Colas Rail UK, Network Rail, and AECOM, delivered a package of works between Shepreth and Cambridge. This multidisciplina

16/05/2025
London Gatwick has announced a major partnership with renewable energy provider Vital Energi to deliver a £250 million decarbonisation programme, aimed at achieving net zero for the airport’s own emissions by 2030.
Under a five-year contract, Vital Energi will help the airport transition away from

16/05/2025
Dale Turner, Director of Procurement and Supply Chain at Skanska UK, has been appointed Chair of the Supply Chain Sustainability School.
Turner succeeds Shaun McCarthy OBE, who co-founded the School in 2012 and has led it since its inception. McCarthy will now transition into a roaming ambassador r

16/05/2025
Dudley's Aluminium has taken a major step in its journey to net zero by installing a large-scale solar energy system at its production facility in Cardiff.
The company partnered with Inspire Green, a renewable energy specialist operating across south Wales and south-west England, to fit 192 high-ef

16/05/2025
If you're searching for architects in Tunbridge Wells, you're likely planning something exciting — from a home extension or renovation to a brand-new build.
At Alex Bryla Architecture, we specialise in bespoke architectural design, offering a fresh and creative approach tailored to the uniq

15/05/2025
A major expansion of the Port of Tilbury has been set in motion as owners Forth Ports has submitted an outline planning application to Thurrock Council for the development of a new port facility, Tilbury3 (T3).
The proposed project will redevelop a 100-acre brownfield site—equivalent to 70 football

15/05/2025
Morgan Sindall Construction has commenced work on a capital works programme at the University of Leeds campus.
It was announced earlier this year that Morgan Sindall has been appointed to the programme, which will entail refurbishment of existing university spaces and entrances as well as reroofing

15/05/2025
Construction has officially begun on the long-awaited Marple Community Hub, a £20 million development that will bring a state-of-the-art leisure, health and library complex to the heart of Stockport.
Local leaders, partners, and the main contractor Willmott Dixon gathered in Marple Memorial Park fo

15/05/2025
Great Places Housing Group recently welcomed senior leaders from Manchester City Council to tour the final phase of its flagship £19.4 million Wiremill Court development in New Islington.
Council Leader Cllr Bev Craig and Cllr Gavin White, Executive Member for Housing and Development, visited the s