Passing Gateway Two: What You Need To Know From An MEP Expert

Gateway Two is a key aspect of building safety and quality.

However, the Building Safety Regulator's (BSR) approval process is causing significant backlogs in UK construction projects.

While indications suggest the BSR itself requires some standardisation and enhanced regulation, many across the built environment aren’t aware of what they can do to increase the likelihood of projects being approved. Dean Loizou, Design Director at Whitecode Consulting, underscores the importance of passing through this critical gateway and reveals crucial guidance and information that will help increase the chances of approval.

According to the Construction Plant-hire Association (CPA), more than 150 high-rise residential construction projects across the UK have been delayed by the BSR's Gateway Two regulatory checkpoint. In fact, a survey undertaken by the association revealed schemes had typically been delayed by up to 40 weeks – compared to the two-week approval timeline that was originally intended.

While we have seen a few of our projects pass this vital checkpoint in recent weeks and months, we are well aware of the substantial impacts Gateway Two is having on the built environment.

With that in mind, I feel it’s pertinent to underline the importance of passing this checkpoint and what designers, consultants, architects and property developers can do to increase the likelihood of doing so.

The vital need to signpost information

There have been many occasions where industry associates have told us their construction projects have been rejected by the BSR because 'there was a lack of information provided'. While, sometimes this is true, there are also repeat instances of all relevant information being provided but it being missed by the individual(s) reviewing the application.

With the BSR having to review huge numbers of project applications, this is perhaps somewhat forgivable. However, it emphasises the need for anyone submitting an application to be as clear as possible and to ‘signpost’ all the vital information to prevent it being missed.

-- Advertisement --
hss

It's also well worth providing a narrative-driven explanation of how each element of the design meets the respective requirements of the Building Regulations. This can be done in the Compliance Statement, a key document that accurately demonstrates compliance through the provision of clear examples and the use of specific standards and codes where possible.

Co-ordination is essential

When it comes to building design, taking a holistic approach can have a major impact on whether a project application passes Gateway Two. For instance, in higher-risk buildings, sprinkler systems and other Contractor Designed Portion (CDP) items will be required to provide enhance fire safety. These products will need to be integrated into building design at the earliest possible opportunity.

Similarly, other safety-critical elements, from fire stopping plans and fire strategies through to waterproofing and structural integrity, will need to be effectively co-ordinated from the outset Doing so will ensure that all these critical aspects of building and fire safety work together effectively – increasing the likelihood of the project application passing Gateway Two.

The other key benefit is that you will have a near complete coordination package between the design team, reducing any issues on site once the build has started.

Plan ahead

Of course, preparing documents in advance and being methodical in your approach is crucial. With the BSR demanding many mandatory documents and items, such as competence declarations, fire emergency files and project and team information, cross-referencing everything and only including what’s relevant to your project can make a huge difference on the speed of BSR assessment and the likelihood of success.

It's also worth bearing in mind the application process isn’t something that takes place overnight. So, account for that when planning and submitting your application. In fact, the BSR actually recommends giving notice up to six months prior to your planned submission. Therefore, it is essential the clients allow sufficient time for the design team to produce and coordinate the information to ensure this is not something picked up by the BSR.

It would also be worth acknowledging and understanding the process for applying to the Secretary of State for a non-determination in case the BSR doesn’t respond within the statutory timeframe.

Consult with experienced specialists

It may sound obvious, but seeking advice and support from experienced consultants and industry experts can make a huge difference to the success or failure of your BSR application. With the Gateway Two approval process an incredibly stringent and time-consuming affair, avoiding rejection cannot be understated.

So, engage specialists in building and fire safety, not to mention compliance, and provide them with all necessary information for them to review designs and documentation before you apply to the BSR. Any weaknesses or potential pain points will be identified early and give you the ideal opportunity to address them before it is too late. This will also prevent much more costly alterations further down the line.

Some of the main MEP Contractor Design Portion (CDP) packages that would need to be engaged for a BSR system include sprinkler systems, fire alarm systems, smoke ventilation systems, dry/wet riser systems, evacuation alert systems, PV systems, secondary supply systems and disabled refuge alarm systems.

At Whitecode Consulting, we specialise in providing clients from across the UK with first class MEP design and sustainability consultancy services. Through our comprehensive and unrivalled support and guidance, we have helped several clients with successful Gateway Two applications.

For more information visit www.whitecode.co.uk

Latest Construction News

26/06/2026
CField Construction has been officially appointed by Fusion Group as main contractor for two major UK residential developments, with a combined contract value of £176 million. The schemes will deliver purpose-built student accommodation (PBSA) and affordable housing in London and Glasgow, with com
Read More
26/06/2026
A permanent riverside link between the Hythe and Rowhedge is back in place after Colchester City Council completed Phase Two of the Fieldgate Quay restoration, drawing a line under years of disruption caused by structural failure and temporary diversions. The last phase concludes repairs to damage
Read More
26/06/2026
Holcim UK has secured a competitive tender to supply sustainable readymix concrete for the Smithfield Lofts residential development in Digbeth, Birmingham’s Creative Quarter, as part of the wider £1.9 billion Smithfield regeneration scheme. The Smithfield Lofts project, delivered by principal contr
Read More
26/06/2026
Galliford Try has been named among the UK's Top 50 Employers of Veterans for 2026, securing 20th place in the prestigious GREAT British Employers of Veterans ranking — an improvement of 20 places on last year. The 50 GREAT British Employers of Veterans is widely regarded as the UK’s leading benchma
Read More
26/06/2026
Councillors Linda Smith and Nigel Chapman joined representatives from OX Place – Oxford City Council's wholly owned housing company – Oxford City Council, Homes England and construction partner Cantay Estates for a ribbon-cutting at Keepers Place on Wednesday 24 June, marking completion of the first
Read More
26/06/2026
A new Community Diagnostic Centre (CDC) at St Margaret's Hospital has officially opened, expanding access to diagnostic services for local residents and supporting efforts to provide healthcare closer to patients' homes. The facility, delivered by Morgan Sindall Construction's Essex business for Th
Read More
26/06/2026
Kensington and Chelsea Council has approved a £1.3 million refurbishment of the near-120-year-old Chelsea swimming pool, aiming to preserve its heritage while cutting energy and water use. Opened in April 1907, the facility will have its pool plant and roof replaced, the swimming pools' surfaces re
Read More
26/06/2026
A major agreement has been concluded with BAM to undertake the initial phase of civil engineering for the northern converter station on the proposed Eastern Green Link 3 (EGL3), marking a significant step forward for what is set to be the UK’s largest electricity transmission project. Through an Ea
Read More
26/06/2026
Phased works will start next week at Northampton Central Library to safeguard the Grade II-listed building, modernise facilities and bring key services together under one roof. The refurbishment will be carried out in stages over the next 12 months so the library and Registration Service can remain
Read More
26/06/2026
Multi-Shower is introducing its maintainable shower system to the UK construction, facilities and building management sectors. Designed as an alternative to traditional fixed spray plate shower heads, Multi-Shower uses a replaceable insert system developed to support routine maintenance and long-te
Read More
Pro Structures LtdLakeside HireBRICOFLOR UKPragmatic Consulting LtdPump SuppliesMark 1 AgenciesAqua Safety ShowersDOORS AND WORKTOPS LTDSpeedy Street Solutions LtdEMKO Industrial (NI) Ltd