Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
09/03/2010

RMD Kwikform's Unique Tyne Tunnel Traveller System

Construction News Image
RMD Kwikform pulled out all the stops to win a contract from Bouygues Travaux Publics and Dunne Building & Civil Engineering for the Tyne Tunnel, creating a unique concept for a 21 metre long, 60 tonne falsework traveller system - in just 7 days.

For formwork and falsework specialist RMD Kwikform, given 7 days to go back to the drawing board, following an unsuccessful bid for an important contract on the Tyne Tunnel, led to the conception of the company’s most innovative travelling tunnel soffit support system to date.

Having secured the deal through Concessionaire TT2's main Design and Build Contractor Bouygues Travaux Publics at the final hour, engineers teamed up with North tunnel section subcontractor, Dunne Building & Civil Engineering, combining expertise to successfully utilise the unique traveller system.

Travelling on the equivalent of train tracks, the RMD Kwikform traveller used a combination of specially designed and standard equipment to create a solid yet flexible structure, capable of snaking up an incline of 6%. Withstanding loads of up to 750 tonnes the traveller was capable of supporting up to 300 cubic metres of concrete poured over 173 square metres.

The 21m long traveller system was used by Dunne Civil Engineering to successfully cast the nine, 1200mm thick roof slabs that make up the roof of the tunnel’s North section for the Tyne Tunnel operator, TT2 who, together with Project Promoter the Tyne and Wear Integrated Transport Authority (TWITA), funded £260m project.

For RMD Kwikform Engineering Director, Ian Fryer who led the four strong engineering design team for the project, overcoming the challenges faced at both the design and utilisation stages of the project were particularly rewarding.

Ian said: "When you are challenged to go back to the drawing board on a project of this scale and importance, it tests all of your engineering knowledge and capabilities.

-- Advertisement --
hss

"The challenge was to deliver a whole-slab-area travelling formwork system with 2 metre height variation which could be operated without the site staff working at height. The traveller also needed to give the users the flexibility to snake the equipment up an incline of 6%, travelling on rails whilst casting a slab that was up to 8.5 metres off the ground, at the bottom of a 25 metre deep excavation full of large ground shoring props.

"Once we had overcome the design element and been awarded the contract by Bouygues Travaux Publics, we entered the phase of taking the proposal design to the end solution. At this time, because the works for the North contract were subcontracted to Dunne Civil Engineering, we had to deal with a new construction team to demonstrate how the system would work.

"At this stage Dunne's were able to assist the design team with suggested amends to the design in order for the system to best meet the needs of the site team. The very tight programme schedule also placed further challenges on the delivery and erection of equipment, which physically required assembling and commissioning 60 tonnes of system and special components at the base of what is effectively a large hole.

"As part of the intensive design and detailing phase that followed, the first thing the team concentrated on was the calculations, detailing, procurement and fabrication of the special items of equipment needed for the project. Shortly followed by production of the general arrangement drawings required for assembly and the detailed instructions for use of the machine.

"Procurement of the special equipment, (which included the hydraulic leg components that were central to the function of the traveller), ultimately determined whether the system could be assembled and operated within the time frame required."

Having developed an assembly sequence in collaboration with Dunne’s for the traveller, RMD Kwikform provided three customer service team members to assist with the erection of the traveller which as a part of the design required the support legs to always be perpendicular to the slope of the soffit.

Unlike previous travellers designed by RMD Kwikform, which incorporated structural steel work at the soffit level, the RMD Kwikform engineering team recognised the opportunity to adapt its R700 truss girder panels for use on this project. By adapting the R700 girders with specially fabricated cantilever frames at the ends, the units were used to span across the tunnel whilst still maintaining sufficient headroom beneath to accommodate site traffic, such as concrete mixers and scissor lifts.

Having to negotiate both varying horizontal and vertical curves, the 21 metre long traveller had to be flexible enough to be able to be travelled around the tunnel profile, rising from its start point at the river side end wall. For this reason RMD Kwikform split the structure into three 7.2m long rectangular tables, which were linked by adjustable bays of equipment that could be changed in length to adjust the horizontal and vertical curvature of the entire assembly and provided sufficient flexibility during travelling to accommodate level tolerances in the running rails.

Advancing up to 21 metres in about an hour, the RMD Kwikform traveller system has reduced the time for slab pouring significantly when compared with traditional methods. This in-turn allowed this section of the project to be completed on-schedule by the end of November 2009.

For further information contact RMD Kwikform on Tel: 01922 743743 or Email: info@rmdkwikform.com

Latest Construction News

03/05/2024

Construction firm GRAHAM has started building work on a £19 million Community Diagnostic Centre (CDC) in Workington town centre. The Centre will be located next to Cumberland Council's government-funded Innovation Hub which is also under development in Central Way. GRAHAM is the principal ...
03/05/2024

Significant progress is being made on a new £2 million recycling centre in Haverhill. Construction works are being completed by FCC Environment and its contractor DXI Regeneration Ltd, on behalf of Suffolk County Council. The facility will be operated by FCC Environment, which manages all of ...
03/05/2024

Midlands contractor G F Tomlinson has started work on a new primary school in Dunstall Park Estate, Tamworth. The work is taking place on behalf of Staffordshire County Council alongside project managers and concept architects, Entrust. The project was procured through the Constructing West ...
03/05/2024

Galliford Try has made another step in its carbon reduction journey with the deployment of a new digital platform across its Infrastructure projects. The platform, Qflow, automates data capture and processing by extracting information from delivery and waste tickets, using Artificial Intelligence ...
03/05/2024

Underfloor heating is the most efficient method of heating a room and is fast becoming the most popular option for new building and property refurbishments. As a result, more trade professionals are being asked to install underfloor heating and self-builders and renovators are using it as their ...
03/05/2024

Farrans is making significant progress at Barsham Water Treatment Works in Suffolk, where its client Essex and Suffolk Water is investing more than £49 million in upgrades to the site. Due to be complete in 2025, the project will provide improvements to the resilience and quality of drinking ...
03/05/2024

Work has been completed on a new bridleway bridge at Lindsells Level Crossing in Biggleswade, Bedfordshire. Work started in December 2022 on the fully accessible bridleway bridge which allows pedestrians, horse riders, cyclists and other users to safely cross the railway line, providing better ...
03/05/2024

Ideal Work UK has unveiled Microtopping®, a revolutionary cementitious coating that delivers the sleek, sophisticated look of polished concrete with unparalleled versatility and ease of application. ...
03/05/2024

Building work has commenced on a new development in Oundle that will bring self-contained extra care apartments to the area along with 62 homes and three self-build plots. Persimmon's East Midlands team have started preparing the Barnwell Walk site off St Christopher’s Drive in the town and expect ...
03/05/2024

Morgan Sindall has been appointed to two new Pagabo frameworks. The two frameworks are valued at £1.6 billion each and will run for four years. It was confirmed earlier this month that Morgan Sindall had been appointed to the new £1.6bn Healthcare Decarbonisation Framework from Pagabo, which has ...
Aqua Direct LtdLakeside HireThink Construction Skills Ltd.JWCEfco UK LtdBRICOFLOR UKTanks For Everything LtdBarrier MartCompass Protection Manufacturing LimitedContainex
Terms and Conditions
2024/05/05 18:29:15